Yes — registered under affordable housingprice caps & eligibility apply
Timeline
Project startedOct 2020
RERA registeredFeb 2021
Proposed completionJun 2025
TodaySep 2026
Construction progress
100% overall, as filed
Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.
Find your flat
Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
126 units across 1 batch
TypeArea sq mCount
Residential & Shop49126
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
2,187 homes · 82 plotson the public record across 31 projects
1,33,437 sq mbuilt-up filed
8,089 sq mplotted area
83,255 sq mland declared
₹292.49 Crdeclared build cost
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Urban Development AuthorityUrban Development Authoritythis project6 of 25 projects
Bhavnagar Municipal CorporationMunicipal / Corporation2 of 25 projects
Gandhinagar Urban Development AuthorityUrban Development Authority2 of 25 projects
Junagadh Municipal CorporationMunicipal / Corporation2 of 25 projects
Others2 of 25 projects
Rajkot Municipal CorporationMunicipal / Corporation2 of 25 projects
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 25 projects
IndoreTown & Country Planning (DTCP)1 of 25 projects
Jamnagar Municipal CorporationMunicipal / Corporation1 of 25 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 25 projects
Pune Municipal Corporation PuneMunicipal Corporation1 of 25 projects
Surat Municipal CorporationMunicipal / Corporation1 of 25 projects
Surat Urban Development AuthorityUrban Development Authority1 of 25 projects
Surendranagar-Wadhvan Urban Development AuthorityUrban Development Authority1 of 25 projects
Vadodara Urban Development AuthorityUrban Development Authority1 of 25 projects
Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Shubh Residency, B/h D-Mart,B/s Hotel Rajwadi Thath, Ahmedabad-Mehsana Highway, Kalol,
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 675m away · Clinic within 2km
LifestyleNo parks within 2km · 3 restaurants and cafes within 1km
ShoppingSupermarket 374m away
Getting around
Primary road 370 mRailway line 1.4 kmRailway station 2.3km away (Kalol Junction)Limited bus connectivity nearby
Water & environment
Water body 1.1 km · Kapileswar TankRiver 1.5 km
distances only — not a flood assessment
Land, title & encumbrance
MortgageLoan outstanding · ₹1.9 Lakh outstanding
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price
₹16.58 Cr declared to build 126 flats. What that works out to:
₹3.70 Lakh – ₹19.00 Lakhdeclared unit pricerange on the filing — not a live asking price
₹13.16 Lakhdeclared cost per flatall-in — land + construction
₹2,498/sq ftof carpet area₹26,887/sq m
12%of the cost is land₹715/sq ft of land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Gujarat Revenue Department — Annual Statement of Rates (jantri), 2011
In Gujarat it’s called the jantri rate — the 2011 book, which is the one in Horizon's record.
₹7,525per sq yd
₹9,000per sq m
Which rate
land + construction: residential flat
Matched to
The rate published for the village of “KALOL”.
In force
2011 schedule
This filing declares ₹26,887 per sq m of carpet area — 2.99× the government figure. Declared cost is land and construction; the government guidance rate is what the state will not register a sale below. Neither is a sale price.
What this number is — and isn’t
The minimum value Gujarat’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
Not a market price. Sales normally register above it, and how far above varies by place and by project.
Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
Government Guidance Rate — done
05
Planning authority
GujRERA · Approved building plan
Ahmedabad Urban Development Authority
Urban Development Authority
Building Permitapproved 22 Feb 2021 · 5 yrs ago
The promised possession date (29 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
Building-Use (BU) permission — the occupancy sign-off, on record
All 2 blocks carry a Building-Use (BU) permission (latest 10 Jan 2025)— Gujarat’s legal-to-occupy sign-off, and the completion proof most RERA records simply don’t carry. Still confirm the BU covers your specific unit before you rely on it.
The approving body, at scale
Ahmedabad Urban Development Authority
Urban Development Authority
Has approved 2,400 RERA projects — about 1 in 7 in Gujarat.
an apartments market — 99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.
Builders
1,936
On record
3,12,468 flats · 1,153 plots
Reach
22 talukas
Since
2007
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
GujRERA's list gives each complaint's number and date, not its status or outcome — and only disputes escalated to GujRERA appear here at all.
Number
What
Date
CMP/A/ONLINE/Gandhinagar/15102025/00532
Complaint · Form A
14 Aug 2025
SMC/NCQER/ONLINE/Gandhinagar/02042025/00066
Non-compliance · quarterly report
9 Dec 2024
What the builder declared
Declared to GujRERA
Litigation
None declared in this filing
Only what the builder declared, or what GujRERA records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with GujRERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
1,505 residential projects still under way within 25 km. Step out ring by ring:
Of the 128 projects the radar draws within 6 km — every kind, every stage — 45 are residential projects still under way. This list keeps only those, and looks further out.