SKYLINE 30

PR1330002600518 · MahaRERA · https://gethorizon.in/projects/skyline-30-juinagar-thane-j4n4zs2w

01

Complete project overview

MahaRERA · Registration filing
Units
248 units
Floors
32
Buildings
4
Parking
971 spaces
Land area
14,569 sq m
Sanctioned built-up
36,517 sq m

Timeline

RERA registeredMay 2026
Proposed completionMar 2033
TodaySep 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

BALAJI JINDAL SPACES LLP

Limited Liability PartnershipPromoter type
Thane, MAHARASHTRABased in
2Projects
1City
2026–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
945 homeson the public record across 2 projects
1,00,080 sq mbuilt-up filed
29,138 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from BALAJI JINDAL SPACES LLP— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Juinagar
Taluka
Thane
District
Thane
Pincode
400705
Survey no.
Plot No. Gen-2/1/E (part)
North boundary
Portions of Plot No. 2/1/D and Plot No. 2/1/E
East boundary
Portion of Plot 2/1/E
South boundary
Existing Nala
West boundary
Existing Nala
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.1km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingSupermarket 1.3km away
Getting around
Expressway 1.9 kmPrimary road 1.6 km · Thane Belapur RoadRailway line 973 m · Trans-Harbour LineRailway station 3.3km away (Seawoods)Bus stop within 1km
Water & environment
Canal 552 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Maharashtra Industrial Development Corporation (MIDC)

Development Authority
Building Permit
Survey no. Plot No. Gen-2/1/E (part)
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra Industrial Development Corporation (MIDC)

Metropolitan / development authority

Has approved 156 RERA projects0.8% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
118
On record
3,504 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

4,734 residential projects still under way within 25 km. Step out ring by ring:

Of the 547 projects the radar draws within 6 km — every kind, every stage — 224 are residential projects still under way. This list keeps only those, and looks further out.

18 projects within 1 km — showing the nearest 6.

40 m awayResidential / Group Housing

T1 Raheja Jade City

NEWFOUND PROPERTIES AND LEASING PRIVATE LIMITED · Navi Mumbai · Thane

Dec 2025registered
Jul 2031target completion
Scale194 flatsAuthorityMahaRERA
40 m awayResidential / Group Housing

T3 Raheja Jade City

NEWFOUND PROPERTIES AND LEASING PRIVATE LIMITED · Navi Mumbai · Thane

Nov 2025registered
Jul 2031target completion
Scale264 flatsAuthorityMahaRERA
40 m awayResidential / Group Housing

T10 Raheja Jade City

NEWFOUND PROPERTIES AND LEASING PRIVATE LIMITED · Navi Mumbai · Thane

Nov 2025registered
Jul 2031target completion
Scale198 flatsAuthorityMahaRERA
170 m awayResidential / Group Housing

Shree Ballaleshwar

Virat And Sanskar Group · Vadghar · Panvel

Nov 2025registered
Dec 2028target completion
Government Guidance Rate₹46,238/sq ydScale60 flatsAuthorityMahaRERA
280 m awayOthers

DELTA STELLAR

NOBLE ORGANICS PVT. LTD. · Navi Mumbai · Thane

Feb 2023registered
Dec 2028target completion
Scale620 flatsAuthorityMahaRERA
320 m awayResidential / Group Housing

Raheja Lunaris-4

Raheja Universal (Pvt.) Ltd. · Navi Mumbai · Thane

Jul 2026registered
Apr 2033target completion
Scale336 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.