HORIZON
Share

T11 Raheja Jade City

P51700080277 · MahaRERA · https://gethorizon.in/projects/t11-raheja-jade-city-navi-mumbai-m-corp-thane-bgeqmlxx

01

Complete project overview

MahaRERA · Registration filing
Units
153 units
Floors
29
Buildings
2
Parking
220 spaces
Land area
4,328 sq m
Sanctioned built-up
12,682 sq m

Timeline

RERA registeredMay 2025
Proposed completionJul 2031
TodaySep 2026
Construction progress
Basement (if any)0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Internal finishes1%
Superstructure16%
Excavation100%
Podiums100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

NEWFOUND PROPERTIES AND LEASING PRIVATE LIMITED

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
5Projects
1City
2025–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,017 homeson the public record across 5 projects
71,835 sq mbuilt-up filed
6,76,039 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from NEWFOUND PROPERTIES AND LEASING PRIVATE LIMITED— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Navi Mumbai (M Corp.)
Taluka
Thane
District
Thane
Pincode
400706
Survey no.
Gen-2/1/D Gen-2/1/E and Gen-2/1/F
North boundary
Gen 2-1B
East boundary
30 mtr wide road
South boundary
D Bldg
West boundary
20 mtr wide road
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 782m away · Clinic within 2km · Pharmacy within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.4km away
ShoppingSupermarket 372m away · Mall 1.2km away · Bank 737m away
Getting around
Expressway 794 mPrimary road 2.1 km · Mahakali ChowkRailway line 1.1 kmRailway station 2.3km away (Seawoods)4 bus stops within 500m
Water & environment
Water body 768 m · Belapur Waterfall Lake
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Maharashtra Industrial Development Corporation (MIDC)

Development Authority
Building Permit
Survey no. Gen-2/1/D Gen-2/1/E and Gen-2/1/F
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra Industrial Development Corporation (MIDC)

Metropolitan / development authority

Has approved 156 RERA projects0.8% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
118
On record
3,504 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

4,509 residential projects still under way within 25 km. Step out ring by ring:

Of the 491 projects the radar draws within 6 km — every kind, every stage — 195 are residential projects still under way. This list keeps only those, and looks further out.

13 projects within 1 km — showing the nearest 6.

Navi MumbaiResidential / Group Housing

T2 Raheja Jade City

NEWFOUND PROPERTIES AND LEASING PRIVATE LIMITED

May 2025registered
Jul 2031target completion
1 open complaintScale208 flatsAuthorityMahaRERA
NerulResidential / Group Housing

Sai World One Residential

Paradise Green-spaces LLP

Aug 2026registered
Dec 2033target completion
Government Guidance Rate₹1,31,941/sq ydScale316 flatsAuthorityMahaRERA
Navi MumbaiOthers

DDSR DREAMWOOD CHS LIMITED

DDSR DREAMWOOD CHS LIMITED

Jul 2025registered
Jun 2028target completion
Scale33 flatsAuthorityMahaRERA
Navi MumbaiOthers

VIHAAN ELEGANZA

VIHAAN DEVELOPERS

Apr 2025registered
Dec 2029target completion
Scale143 flatsAuthorityMahaRERA
NerulResidential / Group Housing

NOVA VISTA

TODAY PRACHAR HOMES LLP

Apr 2026registered
Mar 2032target completion
Government Guidance Rate₹1,31,941/sq ydScale136 flatsAuthorityMahaRERA
Navi MumbaiOthers

MATRIX IMPERIAL

MATRIX LIFESTYLE

Jan 2024registered
Dec 2028target completion
Scale88 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.