ZUBAIR ENCLAVE

P51700055458 · MahaRERA · https://gethorizon.in/projects/zubair-enclave-thane-m-corp-9i1m1s90

01

Complete project overview

MahaRERA · Registration filing
Project name
ZUBAIR ENCLAVE
Units
46 units
Floors
9
Buildings
2
Land area
477 sq m
Sanctioned built-up
1,817 sq m

Timeline

RERA registeredMar 2024
Proposed completionDec 2028
TodaySep 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Solid Waste Manage…0%
Energy managemcnt0%
Electrical meter r…0%
Internal finishes75%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

ROYAL BUILDERS AND DEVELOPERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
5Projects
5Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
224 homes · 68 plotson the public record across 5 projects
12,306 sq mbuilt-up filed
7,674 sq mland declared
₹18.38 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from ROYAL BUILDERS AND DEVELOPERS— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400612
Survey no.
137/13
North boundary
SUMATI APARTMENT
East boundary
9 MTR ROAD
South boundary
ASLAM MANSION
West boundary
OLD MUMBAI PUNE ROAD
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 195m away · 1 clinic within 1km
LifestylePark 1.4km away
ShoppingNo supermarket within 2km
Getting around
Expressway 232 m · Mumbra-Kausa BypassPrimary road 2.8 km · Thane Belapur RoadRailway line 164 m · Mumbai-Pune RailwayRailway station 331m away (Mumbra)8 bus stops within 500m
Water & environment
River 396 mWater body 630 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹60,034per sq yd
₹71,800per sq m
Which rate
residential flat (built)
Matched to
The middle rate across the 101 divisions of “Thane (M Corp.)” — the city's middle, not this project's own division.
In force
2026-2027 schedule
Spread
₹26,923₹1,55,185 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of city, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. 137/13
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

5,323 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,054 projects the radar draws within 6 km — every kind, every stage — 393 are residential projects still under way. This list keeps only those, and looks further out.

4 projects within 1 km — showing the nearest 4.

180 m awayResidential / Group Housing

ALISHAN ARCADE - BUILDING NO. B1

PATANGWALA ASSOCIATES · Thane

May 2022registered
Mar 2027target completion
Government Guidance Rate₹60,034/sq ydScale48 flatsAuthorityMahaRERA
530 m awayResidential / Group Housing

GRAND MERIDIAN CITY

Thalia Land Developers · Mumbra · Thane

Jun 2026registered
Dec 2031target completion
Government Guidance Rate₹39,716/sq ydScale347 flatsAuthorityMahaRERA
830 m awayResidential / Group Housing

FBKA Jewels

FBKA Developers LLP · Thane

Dec 2020registered
Jun 2031target completion
Government Guidance Rate₹60,034/sq ydScale513 flatsAuthorityMahaRERA
830 m awayResidential / Group Housing

DOSTI PLANET NORTH - DOSTI CROWN

CHALAMA INFRAPROPERTIES PRIVATE LIMITED · Thane

Mar 2024registered
Mar 2028target completion
Government Guidance Rate₹60,034/sq ydScale50 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.