01

Complete project overview

MahaRERA · Registration filing
Units
32 units
Floors
5
Buildings
2
Parking
46 spaces
Land area
916 sq m
Sanctioned built-up
1,612 sq m

Timeline

RERA registeredJun 2026
Proposed completionDec 2033
TodaySep 2026
Construction progress
Excavation0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Electrical meter r…0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

A Corporation

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
2Projects
1City
2025–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
32 homeson the public record across 2 projects
6,950 sq mbuilt-up filed
3,299 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Town Planning & Valuation Department,Assistant Director Of Town Planning,Raigad Branch,Raigadthis project1 of 2 projects
Town Planning And Collector RaigadCollector office1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from A Corporation— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Chendhre
Taluka
Alibag
District
Raigarh
Pincode
402201
Survey no.
49/15
North boundary
Plot Survey no 50/14
East boundary
Plot Survey no 51
South boundary
Plot Survey no 45
West boundary
Road
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 538m away · 1 clinic within 1km
LifestylePark 1.2km away
ShoppingNo supermarket within 2km
Getting around
Expressway 613 m · Alibag RoadPrimary road 498 m · Alibaug Rewas RoadRailway line 4.1 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 805 mRiver 1.1 km
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Town Planning & Valuation Department,Assistant Director Of Town Planning,Raigad Branch,Raigad

Building Permit
Survey no. 49/15
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that approved this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

110 residential projects still under way within 25 km. Step out ring by ring:

Of the 104 projects the radar draws within 6 km — every kind, every stage — 33 are residential projects still under way. This list keeps only those, and looks further out.

15 projects within 1 km — showing the nearest 6.

250 m awayResidential / Group Housing

Alibag Nirvana

ACORP · Chendhre · Alibag

Oct 2023registered
Dec 2029target completion
AuthorityMahaRERA
260 m awayResidential / Group Housing

Alibag Divine

A Corporation · Chendhre · Alibag

Jul 2025registered
Dec 2032target completion
AuthorityMahaRERA
360 m awayResidential / Group Housing

Acons The Park Phase 1

Aarun Gulati · Chendhre · Alibag

Oct 2024registered
Dec 2030target completion
Scale83 flatsAuthorityMahaRERA
440 m awayResidential / Group Housing

Indraprastha Building 4

Indraprastha Associates · Gondhalpada · Alibag

Apr 2026registered
Dec 2026target completion
Scale40 flatsAuthorityMahaRERA
530 m awayMixed

Shree Radha Krishna Residency

SHREE RADHA ENTERPRISES · Chendhre · Alibag

Mar 2026registered
May 2027target completion
Scale32 flatsAuthorityMahaRERA
580 m awayMixed

KARNIK SAGAR RESIDENCY

JAYANT KRISHNA SHETH · Chendhre · Alibag

Jul 2026registered
Mar 2030target completion
Scale25 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.