HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
14 spaces
Land area
907 sq m
Sanctioned built-up
2,033 sq m

Timeline

RERA registeredJul 2024
Proposed completionDec 2025
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Street Lighting0%
Fire protection an…0%
Electrical meter r…0%
Open Parking0%
Internal finishes30%
Stairs & lifts60%
Superstructure95%
Excavation100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Pushpam Infra LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
10Projects
3Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
226 homes · 24 plotson the public record across 10 projects
17,906 sq mbuilt-up filed
9,410 sq mplotted area
33,396 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Alibaug Municipal Corporation, RaigadMunicipal Corporation1 of 3 projects
Collector Of RaigadCollector office1 of 3 projects
Dm Raigadthis project1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kawir
Taluka
Alibag
District
Raigarh
Pincode
402201
Survey no.
Gat No. 486, Hissa No. 1 and 2, Plot No. 25 to 31
North boundary
12 Mtr Internal Road
East boundary
9 Mtr Internal Road
South boundary
9 Mtr Internal Road
West boundary
Adj Gat No 485
What’s nearby
SchoolsNo schools within 2km · College or university 1.3km away
HealthcareHospital 652m away · 1 clinic within 1km · Doctor's clinic within 1km
LifestylePark 935m away
ShoppingNo supermarket within 2km
Getting around
Expressway 1.5 km · Alibag RoadPrimary road 861 m · Bypass RoadRailway line 4.3 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 776 mRiver 2.2 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Dm Raigad

Building Permit
Survey no. Gat No. 486, Hissa No. 1 and 2, Plot No. 25 to 31

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.