01
Complete project overview
MahaRERA · Registration filing- Floors
- 7
- Buildings
- 2
- Parking
- 17 spaces
- Land area
- 909 sq m
- Sanctioned built-up
- 1,597 sq m
Timeline
RERA registeredDec 2025
Proposed completionMar 2029
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Basement (if any)10%
Excavation100%
02
Builder’s track record
MahaRERA · Promoter registrationJaydeep Moreshwar Kher
IndividualPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- Kothrud
- Taluka
- Haveli
- District
- Pune
- Pincode
- 411038
- Survey no.
- CTS 987, S.No. 89+90, Plot No. 10
- North boundary
- Plot no 106 and 107
- East boundary
- Plot no 11
- South boundary
- 18 meterswide road
- West boundary
- Plot No 9
What’s nearby
Schools2 schools within 500m · 4 educational institutions within 1km · College or university 1.2km away
HealthcareHospital 163m away · 5 clinics within 1km · Pharmacy within 500m
LifestylePark 1.7km away · Gym or sports centre 1.1km away · 16+ restaurants and cafes within 1km
ShoppingSupermarket 739m away · Convenience store within 1km · Bank 402m away
Getting around
Expressway 1.4 km · Katraj - Dehu Road BypassPrimary road 251 m · Paud RoadMetro station 242m away (Vanaz)6 bus stops within 500m
Water & environment
Water body 1.1 km
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
None on record with MahaRERA against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.