6 extensions on record — latest to 28 Feb 2027declared reason: force majeure
Description
1. The earlier project finish date was 31/03/2020, and now the estimated finish date has been extended to 28/02/2021. The estimated finish date has been approved on 02/07/2019 and changed on 05/07/2019.
2. The total phase area and project area of the project updated on 13-08-2020 as 25657.41 sq.mt. instead of 62345.66 sq.mt. and shall be read as 25657.41 sq.mt. This bears the approval of Honorable Chairman Sir.As per remark the correct phase area has been rectified in Land Details of Registering Project.
Timeline
Construction startJul 2014
RERA registeredSep 2017
Proposed completionFeb 2021
TodaySep 2026
Find your flat
Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
674 units across 51 batches
BuildingTypeArea sq mCount
Green Meadows2BHK TYPE-A5696
Green Meadows3 BHK8048
Green Meadows3 BHK8048
Green Meadows2BHK TYPE-C7011
Green Meadows2BHK TYPE-A5696
Green Meadows2BHK TYPE-A5624
Green Meadows1BHK3757
Green Meadows3BHK8048
Green Meadows1BHK3757
Green Meadows3 BHK8048
Green Meadows3 BHK804
Green MeadowsEWS-07312
Green Meadows2BHK TYPE-A5624
Green MeadowsLIG-06404
Green Meadows2BHK TYPE-B5711
Green MeadowsLIG-06404
Green MeadowsLIG-03372
Green Meadows1BHK3712
Green Meadows2BHK TYPE-B5711
Green MeadowsLIG-04372
Green MeadowsLIG-07472
Green MeadowsEWS-09351
Green MeadowsLIG-04372
Green Meadows2BHK TYPE-C7011
Green MeadowsEWS-05292
Green MeadowsLIG-01351
Green MeadowsEWS-08341
Green MeadowsEWS-06311
Green MeadowsLIG-02361
Green MeadowsLIG-01351
Green MeadowsEWS-04293
Green MeadowsLIG-03372
Green MeadowsEWS-01281
Green MeadowsEWS-10361
Green MeadowsEWS-04293
Green Meadows1BHK3712
Green MeadowsEWS-05292
Green MeadowsEWS-07312
Green MeadowsLIG-07472
Green MeadowsEWS-01281
Green MeadowsEWS-03282
Green MeadowsEWS-06311
Green MeadowsEWS-03282
Green MeadowsLIG-05391
Green MeadowsEWS-02281
Green MeadowsLIG-02361
Green MeadowsEWS-10361
Green MeadowsEWS-02281
Green MeadowsEWS-08341
Green MeadowsLIG-05391
Green MeadowsEWS-09351
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
87/298, 90,92, 129, Shivdaspura, Tonk Road, Hema ki Nangal, Jaipur, Jaipur, 303903
Village
Hema ki Nangal
Taluka
Jaipur
District
Jaipur
Pincode
303903
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 104 mRailway line 419 mRailway station 1.8km away (Sheodaspura Padampura)Limited bus connectivity nearby
Water & environment
Canal 2.6 kmWater body 3.0 km · Chandlai Lake
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price
₹108.05 Cr declared to build 674 flats. What that works out to:
₹16.03 Lakhdeclared cost per flatall-in — land + construction
₹1,610/sq ftof built-up area₹17,331/sq m
17%of the cost is land₹673/sq ft of land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Rajasthan registration department
In Rajasthan it’s called the DLC rate.
No government guidance rate is shown for this project.
Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Planning authority
RAJ-RERA · Approved building plan
Jaipur Development Authority
Development Authority
Building Permitapproved 19 Sep 2017 · 9 yrs ago
The promised possession date (28 Feb 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
The approving body, at scale
Jaipur Development Authority
Development authority
Has approved 644 RERA projects — about 1 in 3 in Rajasthan, more than any other body in the state.
a mixed market — 52% apartments · 48% plotted layouts.
Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017
More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
Not published. RAJ-RERA doesn’t publish a complaints register in the record Horizon reads.
So there is nothing to count here — which is not the same as nothing having been filed.
What the builder declared
Declared to RAJ-RERA
Litigation
None declared in this filing
Only what the builder declared, or what RAJ-RERA records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RAJ-RERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
310 residential projects still under way within 25 km. Step out ring by ring:
Of the 65 projects the radar draws within 6 km — every kind, every stage — 12 are residential projects still under way. This list keeps only those, and looks further out.
1 project between 1 and 3 km — showing the nearest 1.