Complete project overview
RAJ-RERA · Registration filing- Land area
- 5,050 sq m
- Completion deadline extended
- 1 extension on record — latest to 4 Jun 2021declared reason: force majeure
- Description
- The following details have been submitted by the developers After receiving the revised maps have been approved by JDA. 1. The details of previous approved was follows: Previously approved maps(G+4) Revised approved maps(G+4) Total built up area was 8493.83 Sq. Mt. Apartments Previously 162 Revised 184 Car Parking previously 3 Visitors parking 3 Two Wheeler Parking 385 at open area and 188 stilt floor 2. Project cost :- the new project read as following a. Land cost :- 2,75,00,000 b. Development cost :- 12,76,00,000 c. Total project cost :- 15,51,00,000 The maps approved on Dated 05.12.2017 Have been attetched with approved letter under copy of layout approval and building plan approval. The Revised maps approved on Dated 14.03.2018 Have been attetched with approved letter. The above mentioned details are being added on 20.07.2018 The following details have been submitted by the developers After receiving the revised maps have been approved by JDA. on date-14.06.2019 1. The details of previous approved was follows: Previously approved maps(G+4) Revised approved maps(G+8) Previously builtup area 10768.70 sqm. Revised built up area 17832.30 Sq. Mt. Apartments Previously 184 Revised 309 Development cost :- 12,76,00,000 The maps approved on Dated 05.12.2017 & 14.03.2018 Have been attetched with approved letter under copy of layout approval and building plan approval. The Revised maps approved on Dated 14.6.2019 Have been attetched with approved letter. The above mentioned details are being added on 09.09.2019
Timeline
Builder’s track record
RAJ-RERA · Promoter registrationReal Revolution Developers Private Limited
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location & price analysis
RAJ-RERA · Registration filing- Address
- 356, 357, 358, 370/1, Sitapura Industrial Area, Bilwa , Sanganer, Jaipur, 302022
- Village
- Bilwa
- Taluka
- Sanganer
- District
- Jaipur
- Pincode
- 302022
₹25.11 Cr declared. What that works out to:
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Planning authority
RAJ-RERA · Approved building planThe promised possession date (4 Dec 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.