Timeline

RERA registeredAug 2017
Proposed completionDec 2020
TodayJul 2026
Construction progress
Podiums0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Street Lighting0%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Water conservation…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Kuldip Ramesh Baagwe

IndividualPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2017–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
wanwadi
Taluka
Haveli
District
Pune
Pincode
411040
Survey no.
995
North boundary
37
East boundary
18
South boundary
37
West boundary
21
What’s nearby
SchoolsNearest school 1.9km away
HealthcareHospital 655m away · 7 clinics within 1km · Pharmacy within 1km
LifestylePark 563m away · Gym or sports centre 915m away · 3 restaurants and cafes within 1km
ShoppingSupermarket 803m away · Mall 530m away · Bank 594m away
Getting around
Expressway 489 m · Solapur RoadPrimary road 2.3 km · East StreetRailway line 680 m · Pune - Miraj Railway LineRailway station 2.1km away (Ghorpuri)Limited bus connectivity nearby
Water & environment
Canal 130 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 995

The promised possession date (5 Dec 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Municipal Corporation

Municipal corporation

Has approved 1,863 RERA projectsabout 1 in 11 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,351
On record
9,749 flats · 439 plots
Reach
3 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.