Complete project overview

MahaRERA · Registration filing
Floors
7
Buildings
6
Parking
38 spaces
Land area
2,400 sq m
Sanctioned built-up
3,493 sq m

Timeline

RERA registeredDec 2023
Proposed completionDec 2026
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Fire protection an…0%
Electrical meter r…0%
Superstructure53%
Plinth100%
Excavation1000%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Golden Magnum

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
wanwadi
Taluka
Haveli
District
Pune
Pincode
411040
Survey no.
S NO. 53 HIssa No. 5+4A/2
North boundary
S No 53 Hissa No 4 Part
East boundary
6 M Wide Road
South boundary
S No 53 Hissa No 6 plus 7
West boundary
S No 76 and S No 77
What’s nearby
Schools1 school within 1km · Library 1.3km away
HealthcareHospital 364m away · 1 clinic within 1km · Doctor's clinic within 1km
LifestylePark 945m away · 4 restaurants and cafes within 1km
ShoppingSupermarket 605m away · Mall 1.1km away · Bank 760m away
Getting around
Expressway 1.6 km · Solapur RoadPrimary road 1.3 km · Kondhwa MargRailway line 2.2 km · Pune - Miraj Railway LineMetro station 2.7km away (Hadapsar)Bus stop within 500m
04

Planning authority

MahaRERA · Approved building plan

Pmc

Building Permit
Survey no. S NO. 53 HIssa No. 5+4A/2
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pmc

Planning authority

Has approved 114 RERA projects0.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
91
On record
1,806 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation1 case on record, earliest 2011
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.