HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
23
Buildings
8
Parking
1,218 spaces
Land area
14,937 sq m
Sanctioned built-up
41,448 sq m
Recreational open space
5,710 sq m

Timeline

RERA registeredApr 2023
Proposed completionMar 2028
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Landscaping & Tree…0%
Street Lighting0%
Energy managemcnt0%
Open Parking0%
Internal Roads & F…30%
Storm Water Drains30%
Fire protection an…35%
Water conservation…45%
Water Supply55%
Solid Waste Manage…55%
Sewerage (Chamber,…60%
Aggregate area of …67%
Treatment And Disp…75%
Electrical meter r…75%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
Community Building…100%
Flat fit-out200%
External finishes200%
OC-readiness200%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

KOLTE-PATIL DEVELOPERS LIMITED

CompanyPromoter type
Pune, MAHARASHTRABased in
59Projects
7Cities
2017–presentActive
Timelineevery project, start → promised completion
24K OPULAGLITTERATI II24K ATRIAIvy Estate Umang PremierWestern AvenueIvy Estate - Ivy Apartments and Villas and Umang Premiere and Umang PrimoLife Republic Sector R1 - 1st AvenueLITTLE EARTH MASULKAR CITY PHASE 2Redevelopment of Jai Vijay CHSL - Phase IGLITTERATIRedevelopment of Link Palace Premises Co-Op Soc. Ltd. Phase ISTARGAZELITTLE EARTH MASULKAR CITY PHASE 3Ivy Estate-Nia24K StargazeEVARA24K Stargaze - J BuildingVERVEVAAYU24K Stargaze- G BuildingGiga PlatinumK52Little Earth, Kiwale Building C16Little Earth, Kiwale- Building B11Life Republic Sector R13/13th Avenue/Aros/Phase ILife Republic Sector R17A/17A Avenue-Sound of Soul/Phase-IALORALife Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops24K Altura - Tower A and B45 WestLife Republic Sector R22/22nd Avenue - Atmos/Phase - ILife Republic Sector R31/31st Avenue/24K-Espada24K Manor - Tower AALERIA - BLOCK B24K Manor - Tower B24K Altura - Tower DLittle Earth, Kiwale - Building C14Little Earth, Kiwale - Building C13Life Republic Sector R22/22nd Avenue - Atmos/Phase-IIGiga Platinum - Tower BSPRINGSHIRELife Republic Sector R5/5th Avenue - Canvas/Phase I24K Altura - Tower CLittle Earth, Kiwale - Building D1Little Earth, Kiwale - Buildng D224K Manor - Tower C and ShopsLife Republic Sector R34/34th Avenue - Duet/Phase ILife Republic Sector R35/35thAvenue Harmony ResidencyLIFE REPUBLIC SECTOR R17A/17A AVENUE-SOUND OF SOUL/SOUND SQUARELIFE REPUBLIC SECTOR R14/14TH AVENUE - QRIOUS/PHASE - ILIFE REPUBLIC SECTOR R34/34TH AVENUE-DUET/PHASE - IIElixir - Phase ISERENOVALIFE REPUBLIC SECTOR R5/5TH AVENUE-CANVAS/PHASE-IILIFE REPUBLIC SECTOR R14/14TH AVENUE - QRIOUS/PHASE – IILIFE REPUBLIC SECTOR R31/31st AVENUE – ECHOES/PHASE – 1VIVERETHE WINDS PHASE-1, SECTOR 1B AT AVIAN VALLEYLittle Earth, Kiwale - Building B7
Builder DNAthe whole portfolio, summed
4,481 homeson the public record across 59 projects
16,28,237 sq mbuilt-up filed
6,68,403 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pune Metropolitan Region Development AuthorityMetropolitan Development Authoritythis project16 of 39 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation8 of 39 projects
Municipal Corporation of Greater MumbaiMunicipal Corporation6 of 39 projects
Pune Municipal CorporationMunicipal Corporation6 of 39 projects
Pune Mahanagar Palika1 of 39 projects
Pune Metroploitan Region Developement Authority1 of 39 projects
Pune Metropolitian Region Development AuthorityMetropolitan Development Authority1 of 39 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Jambe
Taluka
Mulshi
District
Pune
Pincode
411057
Survey no.
91/1P, 91/2P, 91/3P, 91/4P, 91/5P, 91/6P, 91/7P, 91/8P, 91/9P
North boundary
Township boundary S No 52 and others
East boundary
Township boundary S No 91 P Punawale PCMC
South boundary
18 Mtr RP Road
West boundary
Township Boundary
What’s nearby
SchoolsNearest school 1.1km away · College or university 1.6km away · Library 1.7km away
HealthcareHospital 842m away · 1 clinic within 1km · Pharmacy within 1km
LifestylePark 1.6km away · Gym or sports centre 834m away · 30+ restaurants and cafes within 1km
ShoppingSupermarket 751m away · Mall 725m away · ATM within 500m
Getting around
Expressway 606 m · Mumbai - Satara HighwayPrimary road 42 m · Hinjawadi RoadMetro station 547m away (Jakat Naka)5 bus stops within 500m
Water & environment
River 892 m · Mula
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Metropolitan Region Development Authority

Metropolitan Development Authority
Building Permit
Survey no. 91/1P, 91/2P, 91/3P, 91/4P, 91/5P, 91/6P, 91/7P, 91/8P, 91/9P
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 1,013 RERA projectsabout 1 in 20 in Maharashtra.

an apartments market87% apartments · 13% plotted layouts. Apartments like yours are this body's core business.

Builders
604
On record
21,940 flats · 10,299 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation15 cases on record, earliest 2005
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.