HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
24 spaces
Land area
413 sq m
Sanctioned built-up
1,725 sq m

Timeline

RERA registeredOct 2023
Proposed completionJun 2026
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

Ranjana Prakash Jagnade

IndividualPromoter type
Raigarh, MAHARASHTRABased in
1Projects
1City
2023–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Panvel
Taluka
Panvel
District
Raigarh
Pincode
410206
Survey no.
C.T.S. No. 646/C and 647/C, At Panvel, Tal Panvel, Dist Raigad
North boundary
CTS no 646A 646B 647A 647B
East boundary
CTS no 643 CTS no 644 1 and 2
South boundary
CTS 641 1
West boundary
9 mtr wide road
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 810m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 156 mPrimary road 107 mRailway line 131 mRailway station 213m away (Taloje Panchanand)Limited bus connectivity nearby
Water & environment
Water body 874 mRiver 1.8 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Panvel Municipal Corporation

Municipal Corporation
Building Permit
Survey no. C.T.S. No. 646/C and 647/C, At Panvel, Tal Panvel, Dist Raigad

The promised possession date (30 Jun 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Panvel Municipal Corporation

Municipal corporation

Has approved 305 RERA projects1.5% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
238
On record
4,602 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.