Complete project overview

MahaRERA · Registration filing
Plots
58 plots
Land area
15,157 sq m
Recreational open space
1,474 sq m

Timeline

RERA registeredJan 2023
Proposed completionDec 2025
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

Wadhwa Construction and Infrastructure Private Limited

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
28Projects
1City
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,586 homes · 509 plotson the public record across 28 projects
2,57,652 sq mbuilt-up filed
1,63,402 sq mplotted area
2,17,129 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Wardoli
Taluka
Panvel
District
Raigarh
Pincode
410206
Survey no.
70/2,70/3,71/1(pt),71/3(pt),71/2A(pt)
North boundary
ITP Boundary-Private land
East boundary
Private property-NUSI
South boundary
18m wide road
West boundary
Government land
What’s nearby
SchoolsNearest school 1.1km away
HealthcareHospital 194m away · 3 clinics within 1km
LifestyleNo parks within 2km · 3 restaurants and cafes within 1km
ShoppingSupermarket 789m away
Getting around
Expressway 409 mPrimary road 690 mRailway line 472 m · Panvel SidingsRailway station 1.7km away (Khandeshwar)2 bus stops within 500m
Water & environment
Water body 60 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

City and Industrial Development Corporation (CIDCO)

Development Authority
Layout Permit
Survey no. 70/2,70/3,71/1(pt),71/3(pt),71/2A(pt)

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

City and Industrial Development Corporation (CIDCO)

Metropolitan / development authority

Has approved 885 RERA projectsabout 1 in 23 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Layouts like yours are the smaller share here — this body mostly approves apartments.

Builders
724
On record
7,061 flats · 987 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation7 cases on record, earliest 2009
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.