HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Land area
4,200 sq m

Timeline

Construction startAug 2019
RERA registeredSep 2019
Proposed completionMar 2021
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

ANUJ SHARMA

IndividualPromoter type
Jaipur, RajasthanBased in
2Projects
1City
2019–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
36 plotson the public record across 2 projects
11,600 sq mplotted area
11,600 sq mland declared
₹2.73 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
1520, VILLAGE SIROLI TEHSIL SANAGANER, SIROLI, Sanganer, Jaipur, 302023
Village
SIROLI
Taluka
Sanganer
District
Jaipur
Pincode
302023
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.6km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Railway line 3.9 kmRailway station 4.0km away (Khatipura)Limited bus connectivity nearby
Water & environment
Water body 3.2 km · Dravyavati River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹1.53 Cr declared. What that works out to:

₹339/sq ftof plotted area₹3,647/sq m
69%of the cost is land₹235/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Layout Permitapproved 11 Sep 2019 · 6 yrs ago

The promised possession date (31 Mar 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.