HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
3
Buildings
4
Parking
24 spaces
Land area
1,375 sq m
Sanctioned built-up
2,337 sq m

Timeline

RERA registeredJun 2023
Proposed completionMay 2028
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Water conservation…30%
Electrical meter r…50%
OC-readiness70%
Flat fit-out80%
Stairs & lifts80%
External finishes80%
Excavation100%
Plinth100%
Superstructure100%
Internal finishes100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Landscaping & Tree…100%
Street Lighting100%
Treatment And Disp…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

KUNDALWAL BUILDERS LLP

PartnershipPromoter type
Aurangabad, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Aurangabad (M Corp.)
Taluka
Aurangabad
District
Aurangabad
Pincode
431001
Survey no.
PLOT NO. 19 TO 30, GUT NO. 166 PART, SATARA
North boundary
PART OF LANDGUT NO 166
East boundary
6 METER WIDE ROAD LAND OF GUT NO 165
South boundary
6 METER WIDE ROAD
West boundary
PLOT NO 13 TO 18 6 METER WIDE ROAD
What’s nearby
SchoolsNearest school 1.4km away
HealthcareHospital 1.7km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 838 mPrimary road 4.6 km · CIDCO FlyoverRailway line 1.8 kmRailway station 3.3km away (Mukundawadi)Limited bus connectivity nearby
Water & environment
Water body 2.9 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Aurangabad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. PLOT NO. 19 TO 30, GUT NO. 166 PART, SATARA
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Aurangabad Municipal Corporation

Municipal corporation

Has approved 54 RERA projects0.3% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
53
On record
324 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.