Complete project overview

RERA Telangana · Registration filing
Units
20 units
Unit mix
10 × 1BHK, 5 × 2BHK, 4 × 3BHK, 1 × 3 Hbk
Saleable area
64–104 sq mper unit, as filed
Floors
5
Land area
669 sq m
Built-up area
1,996 sq m

Timeline

RERA approvedFeb 2021
Proposed completionFeb 2027
TodayJul 2026
Construction progress

0% overall, as filed

Excavation0%
Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

20 of 20 available
BuildingFloorTypeArea sq mAvailable
TOWER II13BHK1041 of 1
TOWER II11BHK641 of 1
TOWER II12BHK821 of 1
TOWER II11BHK741 of 1
TOWER II23BHKmortgaged1041 of 1
TOWER II21BHKmortgaged641 of 1
TOWER II21BHKmortgaged741 of 1
TOWER II22BHK821 of 1
TOWER II33BHK1041 of 1
TOWER II31BHK642 of 2
TOWER II32BHK821 of 1
TOWER II43 Hbk1041 of 1
TOWER II41BHK642 of 2
TOWER II42BHK821 of 1
TOWER II53BHK1041 of 1
TOWER II51BHK642 of 2
TOWER II52BHK821 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

NEW ERA CONSTRUCTIONS

PartnershipPromoter type
Hyderabad, TelanganaBased in
2Projects
1City
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
35 homeson the public record across 2 projects
3,587 sq mbuilt-up filed
1,299 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
MAILARRDEVPALLY VILLAGE
Village
Mailardevpally
Mandal
Rajendranagar
District
Ranga Reddy
Pincode
500005
North boundary
NEIGHBOURS
East boundary
Others - NEIGHBOURS
South boundary
Others - NEIGHBOURS
West boundary
ROAD WIDTH - 9
What’s nearby
SchoolsNearest school 1.7km away · College or university 1.4km away
HealthcareHospital 399m away · 2 clinics within 1km
LifestylePark 1.5km away
ShoppingNo supermarket within 2km
Getting around
Expressway 280 mPrimary road 693 m · Inner Ring RoadRailway line 357 mRailway station 1.4km away (NPA Shivaram Pally)Limited bus connectivity nearby
Water & environment
Water body 946 m · Palle Cheruvu
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 2/C11/01650/2021Survey no. 161/P AND 162/P
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 2/C11/01650/2021 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.