Complete project overview

ORERA · Registration filing
Units
80 units
Carpet area
67–83 sq mper-unit range, as filed
Building type
S+4
Parking
81 spaces
Land area
4,052 sq m
Plan valid until
21 Mar 2026
Amenities
11 filed — Water Supply, Fire Fighting Facility, Emergency Evacuation Services, Use of Renewable Energy, Elevators, Community Center …
Description
( Residential Project, S+4, No of Units - 80 )

Timeline

Construction startDec 2021
Proposed completionSep 2024
TodayJul 2026

Find your flat

Every flat the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitTypeCarpet sq m
1011ST FLOOR81.94
1021ST FLOOR68.93
1031ST FLOOR68.93
1041ST FLOOR68.93
1051ST FLOOR68.93
1061ST FLOOR69.95
1071ST FLOOR69.02
1081ST FLOOR69.02
1091ST FLOOR81.94
1101ST FLOOR67.44
1111ST FLOOR67.44
1121ST FLOOR81.38
2052ND FLOOR68.93
2062ND FLOOR69.95
2072ND FLOOR69.02
2082ND FLOOR69.02
2092ND FLOOR81.94
2102ND FLOOR67.44
2112ND FLOOR67.44
2122ND FLOOR81.38
2012ND FLOOR81.94
2022ND FLOOR68.93
2032ND FLOOR68.93
2042ND FLOOR68.93
3093RD FLOOR81.94
3103RD FLOOR67.44
3113RD FLOOR67.44
3123RD FLOOR81.38
3013RD FLOOR81.94
3023RD FLOOR68.93
3033RD FLOOR68.93
3043RD FLOOR68.93
3053RD FLOOR68.93
3063RD FLOOR69.95
3073RD FLOOR69.02
3083RD FLOOR69.02
4044TH FLOOR68.93
4104TH FLOOR67.44
4014TH FLOOR81.94
4024TH FLOOR68.93
4034TH FLOOR68.93
4054TH FLOOR68.93
4064TH FLOOR69.95
4074TH FLOOR69.02
4084TH FLOOR69.02
4094TH FLOOR81.94
4114TH FLOOR67.44
4124TH FLOOR81.38
1131ST FLOOR81.75
1141ST FLOOR81.75
1151ST FLOOR81.75
1161ST FLOOR68.37
1171ST FLOOR68.65
1181ST FLOOR68.65
1191ST FLOOR81.10
1201ST FLOOR82.77
2132ND FLOOR81.75
2142ND FLOOR81.75
2152ND FLOOR81.75
2162ND FLOOR68.37
2172ND FLOOR68.65
2182ND FLOOR68.65
2192ND FLOOR81.10
2202ND FLOOR82.77
3183RD FLOOR68.65
3143RD FLOOR81.75
3133RD FLOOR81.75
3153RD FLOOR81.75
3163RD FLOOR68.37
3203RD FLOOR82.77
3173RD FLOOR68.65
3193RD FLOOR81.10
4134TH FLOOR81.75
4144TH FLOOR81.75
4154TH FLOOR81.75
4164TH FLOOR68.37
4174TH FLOOR68.65
4184TH FLOOR68.65
4194TH FLOOR81.10
4204TH FLOOR82.77

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. Carpet area is the legally meaningful number — not the super built-up figure a brochure quotes.

02

Builder’s track record

ORERA · Promoter registration

SS GREEN INFRA DEVELEOPERS

Company/FirmPromoter type
Balangir, OdishaBased in
1Projects
1City
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

ORERA · Registration filing
District
Balangir
Pincode
767001
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 458m away · 4 clinics within 1km · Doctor's clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.7 kmPrimary road 432 mRailway line 2.1 kmRailway station 2.3km away (Bargarh Road)Limited bus connectivity nearby
Water & environment
Water body 109 mCanal 1.1 km
distances only — not a flood assessment
Land, title & encumbrance
Land parcels2 parcels · 4,052 sq m total
Land tenure2 of 2 parcels held under a Power of Attorney / development agreement — not a registered sale deed to the promoter
VillagesBALANGIR 'KHA', BOLANGIR 'KHA'
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

ORERA · Approved building plan

Special Planning Authority, Balangir

Building Permit

The promised possession date (10 Sep 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Special Planning Authority, Balangir

Planning authority

Has approved 14 RERA projects1.2% of Odisha.

a plotted-layout market29% apartments · 71% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
10
On record
338 flats · 547 plots
Reach
4 pincodes
Since
2019

More layout-heavy than Odisha overall — 71% plots here vs 13% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — ORERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — ORERA does not publish a complaints register. This read cannot speak to them either way.