Complete project overview

MahaRERA · Registration filing
Floors
4
Buildings
2
Land area
3,265 sq m
Sanctioned built-up
4,217 sq m
Recreational open space
326 sq m

Timeline

RERA registeredMay 2022
Proposed completionJan 2026
TodayJul 2026
Construction progress
Podiums0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Street Lighting0%
Water conservation…0%
Aggregate area of …0%
Stilt floor60%
Superstructure60%
Internal finishes60%
Flat fit-out60%
Stairs & lifts60%
External finishes60%
OC-readiness60%
Basement (if any)70%
Plinth70%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

RUDRA CONSTRUCTIONS

PartnershipPromoter type
Aurangabad, MAHARASHTRABased in
11Projects
4Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
391 homeson the public record across 11 projects
60,372 sq mbuilt-up filed
23,841 sq mland declared
₹103.10 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Patna Metropolitan Area AuthorityMetropolitan / Development Authority2 of 5 projects
Aurangabad Municipal CorporationMunicipal Corporationthis project1 of 5 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority1 of 5 projects
NAGAR PARISHAD DANAPUR NIZAMATMunicipal / Corporation1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Devlai
Taluka
Aurangabad
District
Aurangabad
Pincode
431010
Survey no.
GUT NO 140 DEVLAI AURANGABAD
North boundary
LAND AT GUT NO 139
East boundary
REMAINING PART OF LAND AT GUT NO 140
South boundary
9 METER VIDE ROAD
West boundary
REMAINING PART OF LAND GUT NO 140
What’s nearby
Schools1 school within 500m · 3 educational institutions within 1km · College or university 570m away
HealthcareHospital 177m away · 5 clinics within 1km
LifestylePark 822m away · 7 restaurants and cafes within 1km
ShoppingSupermarket 1.8km away · Mall 802m away · Convenience store within 500m
Getting around
Expressway 181 m · Jalna RoadPrimary road 1.6 km · Kranti ChowkRailway line 2.7 kmRailway station 3.1km away (Mukundawadi)Bus stop within 500m
04

Planning authority

MahaRERA · Approved building plan

Aurangabad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. GUT NO 140 DEVLAI AURANGABAD

The promised possession date (20 Jan 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Aurangabad Municipal Corporation

Municipal corporation

Has approved 54 RERA projects0.3% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
53
On record
324 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.