Description
Sanroyal Clair City

Timeline

Project startedFeb 2019
RERA registeredJun 2024
Proposed completionApr 2030
TodayJul 2026
Construction progress

30% overall, as filed

Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Electrical Fittings0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Basement(s) and Plinth0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings0%
Electrical Fittings0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings1%
Electrical Fittings10%
The external plumbing and external plastering10%
Electrical Fittings10%
Excavation10%
Excavation10%
Basement(s) and Plinth10%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings10%
The external plumbing and external plastering10%
Electrical Fittings30%
Sanitary Fittings40%
Electrical Fittings40%
Sanitary Fittings40%
Electrical Fittings40%
Sanitary Fittings40%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings70%
The external plumbing and external plastering70%
The external plumbing and external plastering80%
Electrical Fittings85%
Sanitary Fittings85%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings85%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings85%
The external plumbing and external plastering85%
Sanitary Fittings90%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings90%
The external plumbing and external plastering90%
Sanitary Fittings90%
Electrical Fittings90%
Electrical Fittings90%
The external plumbing and external plastering90%
Sanitary Fittings95%
Electrical Fittings95%
Sanitary Fittings95%
Excavation100%
Basement(s) and Plinth100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Electrical Fittings100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Excavation100%
Basement(s) and Plinth100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Excavation100%
Basement(s) and Plinth100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Excavation100%
Basement(s) and Plinth100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

19 of 63 available
TypeArea sq mAvailable
Bangalow / Villas911 of 3
Bangalow / Villas731 of 2
Bangalow / Villas1300 of 1
Bangalow / Villas740 of 5
Bangalow / Villas1171 of 4
Bangalow / Villas972 of 3
Bangalow / Villas681 of 3
Bangalow / Villas1021 of 2
Bangalow / Villas1251 of 2
Bangalow / Villas1011 of 3
Bangalow / Villas1072 of 3
Bangalow / Villas951 of 2
Bangalow / Villas1110 of 1
Bangalow / Villas852 of 6
Bangalow / Villas1390 of 1
Bangalow / Villas1041 of 2
Bangalow / Villas1250 of 1
Bangalow / Villas1250 of 2
Bangalow / Villas1670 of 1
Bangalow / Villas1210 of 1
Bangalow / Villas1530 of 1
Bangalow / Villas1510 of 1
Bangalow / Villas1051 of 2
Bangalow / Villas1590 of 1
Bangalow / Villas960 of 2
Bangalow / Villas750 of 1
Bangalow / Villas1380 of 1
Bangalow / Villas1011 of 2
Bangalow / Villas1050 of 1
Bangalow / Villas910 of 1
Bangalow / Villas1211 of 1
Bangalow / Villas1341 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

SANROYAL BUILDERS AND CONTRACTORS PVT LTD

CompanyPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
15Projects
1Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
700 homes · 67 plotson the public record across 15 projects
64,522 sq mbuilt-up filed
15,935 sq mplotted area
38,141 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thrissur Municipal CorporationMunicipal Corporation3 of 14 projects
Kadinamkulam Grama PanchayatGrama Panchayat2 of 14 projects
Thiruvananthapuram Municipal CorporationMunicipal Corporation2 of 14 projects
Adat Grama PanjayathLocal body (LSGI)1 of 14 projects
Adat Gramma PanchayathLocal body (LSGI)1 of 14 projects
Guruvayur MuncipalityLocal body (LSGI)1 of 14 projects
LsgiLocal body (LSGI)1 of 14 projects
Nadathara PanchayathLocal body (LSGI)1 of 14 projects
Trivandrum Municipal CorporationMunicipal Corporation1 of 14 projects
Vembayam Grama PanchayatGrama Panchayatthis project1 of 14 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
VATTAKARIKKAKOM
Village
VATTAPPARA
Taluk
Nedumangad
District
Thiruvananthapuram
Pincode
695562
Survey no.
455/1
Patta no.
1954
What’s nearby
Schools1 school within 500m · Library 1.5km away
HealthcareHospital 274m away
LifestyleNo parks within 2km · 9 restaurants and cafes within 1km
ShoppingSupermarket 186m away · Bank 180m away
Getting around
Primary road 127 m · MC RoadNo metro or railway within 5km2 bus stops within 500m
Water & environment
Water body 547 mCanal 2.2 km
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Vembayam Grama Panchayat

Grama Panchayat
approved 14 Feb 2019 · 7 yrs ago
Layout Permit no. A4-BA(34009)2019Survey no. 455/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan A4-BA(34009)2019 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Vembayam Grama Panchayat

Grama panchayat

Has approved 7 RERA projects0.5% of Kerala.

a plotted-layout market29% apartments · 71% plotted layouts. Your plotted layout is this body's core business.

Builders
5
On record
0 flats · 104 plots
Since
2021

More layout-heavy than Kerala overall — 71% plots here vs 19% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.