01
Complete project overview
RERA Karnataka · Registration filing- Status
- New Project Launch
- Plots
- 360 plots
- Land parcels
- 12 survey nos
Timeline
Proposed completionOct 2027
Construction progress100% overall, as filed
From the promoter's latest quarterly progress report filed with RERA Karnataka — % complete overall and by stage, as of that filing. A dated snapshot, not a live tracker. UnitTypeTotal sq m
1Plot111.48
2Plot111.48
3Plot111.48
4Plot111.48
5Plot111.48
6Plot111.48
7Plot111.48
8Plot111.48
9Plot111.48
10Plot111.48
11Plot111.48
12Plot111.48
13Plot111.48
14Plot111.48
15Plot111.48
16Plot111.48
17Plot111.48
18Plot111.48
19Plot111.48
20Plot118.38
21Plot132.43
22Plot125.42
23Plot125.42
24Plot125.42
25Plot125.42
26Plot125.42
27Plot125.42
28Plot125.42
29Plot125.42
30Plot125.42
31Plot125.42
32Plot125.42
33Plot125.42
34Plot125.42
35Plot178.17
36Plot196.71
37Plot222.97
38Plot222.97
39Plot222.97
40Plot222.97
41Plot222.97
42Plot222.97
43Plot222.97
44Plot222.97
45Plot222.97
46Plot222.97
47Plot222.97
48Plot222.97
49Plot222.97
50Plot209.15
51Plot106.20
52Plot111.48
53Plot111.48
54Plot111.48
55Plot111.48
56Plot111.48
57Plot111.48
58Plot111.48
59Plot111.48
60Plot111.48
61Plot111.48
62Plot111.48
63Plot111.48
64Plot111.48
65Plot111.48
66Plot111.48
67Plot178.52
68Plot168.08
69Plot125.42
70Plot125.42
71Plot125.42
72Plot125.42
73Plot125.42
74Plot125.42
75Plot125.42
76Plot125.42
77Plot125.42
78Plot125.42
79Plot125.42
80Plot125.42
81Plot125.42
82Plot125.42
83Plot125.42
84Plot132.36
85Plot137.28
86Plot111.48
87Plot111.48
88Plot111.48
89Plot111.48
90Plot111.48
91Plot111.48
92Plot111.48
93Plot111.48
94Plot111.48
95Plot111.48
96Plot111.48
97Plot111.48
98Plot111.48
99Plot111.48
100Plot111.48
101Plot100.30
102Plot184.49
103Plot111.48
104Plot111.48
105Plot111.48
106Plot111.48
107Plot111.48
108Plot111.48
109Plot111.48
110Plot111.48
111Plot111.48
112Plot111.48
113Plot111.48
114Plot111.48
115Plot111.48
116Plot111.48
117Plot148.11
118Plot166.82
119Plot111.48
120Plot111.48
121Plot111.48
122Plot111.48
123Plot111.48
124Plot111.48
125Plot111.48
126Plot111.48
127Plot111.48
128Plot111.48
129Plot111.48
130Plot111.48
131Plot111.48
132Plot111.48
133Plot136.84
134Plot121.21
135Plot125.42
136Plot125.42
137Plot125.42
138Plot125.42
139Plot125.42
140Plot125.42
141Plot125.42
142Plot125.42
143Plot125.42
144Plot125.42
145Plot125.42
146Plot125.42
147Plot125.42
148Plot125.42
149Plot200.66
150Plot197.80
151Plot111.48
152Plot111.48
153Plot111.48
154Plot111.48
155Plot111.48
156Plot111.48
157Plot111.48
158Plot111.48
159Plot111.48
160Plot111.48
161Plot111.48
162Plot111.48
163Plot111.48
164Plot170.06
165Plot158.61
166Plot125.42
167Plot125.42
168Plot125.42
169Plot125.42
170Plot125.42
171Plot125.42
172Plot125.42
173Plot125.42
174Plot125.42
175Plot125.42
176Plot125.42
177Plot125.42
178Plot125.42
179Plot235.41
180Plot117.30
181Plot111.48
182Plot111.48
183Plot111.48
184Plot111.48
185Plot111.48
186Plot111.48
187Plot111.48
188Plot111.48
189Plot111.48
190Plot111.48
191Plot111.48
192Plot111.48
193Plot111.48
194Plot111.48
195Plot91.75
196Plot196.14
197Plot125.42
198Plot125.42
199Plot125.42
200Plot125.42
201Plot125.42
202Plot125.42
203Plot125.42
204Plot125.42
205Plot125.42
206Plot125.42
207Plot125.42
208Plot125.42
209Plot125.42
210Plot144.84
211Plot228.02
212Plot162.82
213Plot158.04
214Plot200.12
215Plot186.41
216Plot130.12
217Plot130.12
218Plot130.12
219Plot130.12
220Plot130.12
221Plot137.04
222Plot149.18
223Plot130.12
224Plot130.12
225Plot130.12
226Plot130.12
227Plot130.12
228Plot130.17
229Plot191.05
230Plot139.35
231Plot139.35
232Plot139.35
233Plot139.35
234Plot139.35
235Plot139.35
236Plot139.35
237Plot139.35
238Plot139.35
239Plot139.35
240Plot139.35
241Plot139.35
242Plot139.35
243Plot139.35
244Plot139.35
245Plot139.56
246Plot155.42
247Plot97.75
248Plot97.75
249Plot97.75
250Plot97.75
251Plot97.75
252Plot97.75
253Plot97.75
254Plot97.75
255Plot97.75
256Plot97.75
257Plot97.75
258Plot97.75
259Plot97.75
260Plot97.75
261Plot108.61
262Plot122.72
263Plot125.42
264Plot125.42
265Plot125.42
266Plot125.42
267Plot125.42
268Plot125.42
269Plot125.42
270Plot115
271Plot71.71
272Plot75.18
273Plot97.75
274Plot97.75
275Plot97.75
276Plot97.75
277Plot97.75
278Plot97.75
279Plot100.10
280Plot237.89
281Plot188.88
282Plot169.45
283Plot150.02
284Plot130.59
285Plot111.16
286Plot91.73
287Plot63.38
288Plot184.76
289Plot131.87
290Plot134.51
291Plot137.15
292Plot165.70
293Plot145.44
294Plot148.08
295Plot150.72
296Plot153.35
297Plot155.99
298Plot158.63
299Plot161.26
300Plot163.90
301Plot166.54
302Plot169.17
303Plot171.81
304Plot174.45
305Plot177.08
306Plot240.08
307Plot244.76
308Plot219.61
309Plot211.70
310Plot139.35
311Plot139.35
312Plot139.35
313Plot139.35
314Plot139.35
315Plot139.35
316Plot139.35
317Plot139.35
318Plot139.35
319Plot139.35
320Plot139.35
321Plot139.35
322Plot139.35
323Plot139.35
324Plot139.35
325Plot139.35
326Plot139.35
327Plot139.35
328Plot139.35
329Plot139.35
330Plot188.55
331Plot181.96
332Plot139.35
333Plot139.35
334Plot139.35
335Plot139.35
336Plot139.35
337Plot139.35
338Plot139.35
339Plot139.35
340Plot139.35
341Plot139.35
342Plot139.35
343Plot139.35
344Plot139.35
345Plot139.35
346Plot139.35
347Plot139.35
348Plot139.35
349Plot139.35
350Plot139.35
351Plot139.35
352Plot264.79
353Plot151.19
354Plot111.48
355Plot111.48
356Plot111.48
357Plot111.48
358Plot111.48
359Plot111.48
360Plot111.48
Complete project overview — done
02
Builder’s track record
RERA Karnataka · Promoter registrationMERU PRAVAT STRUCTURE PRIVATE LIMITED
CompanyPromoter type
Bengaluru UrbanBased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion
202220232024202520262027today
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Builder's track record — done
03
Location & price analysis
RERA Karnataka · Registration filing- Taluk
- Maluru
- District
- Kolar
- Pincode
- 563163
- Address
- SY.NO. 61/1, 62/10, 66/3, 95/1, 96/1, 96/2, 96/3, 96/4, 96/5, 97/1, 97/2, 216/2B WITH AN EXTENT OF 21A33G , AT SAMPANGERE VILLAGE, LAKKUR HOBLI, , Maluru , Kolar, Karnataka - 563163
What’s nearbySchoolsNo schools within 2km
HealthcareNearest hospital 4.9km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting aroundExpressway 4.5 km · Dabaspete - Hosur HighwayPrimary road 1.8 km · Malur - Hosur RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environmentWater body 2.3 km
distances only — not a flood assessment Land, title & encumbranceLandOwned by the promoter
ConversionConverted to non-agricultural
LitigationDeclared free of litigation
MortgageNone declared on the project / land
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict. Price analysisdeclared build cost — not a sale price
₹88.78 Cr declared to build 360 plots. What that works out to:
₹24.66 Lakhdeclared cost per plotall-in — land + construction
80%of the cost is land
Location & price analysis — done
04
Planning authority
RERA Karnataka · Approved building planKolar Urban Development Authority
Urban Development Authorityapproved 26 Nov 2019 · 6 yrs ago
Layout Permit no. MPAVA/64/2015-16Survey no. 61/1
The occupancy certificate — the proof that isn’t hereA sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
Verify it yourself — look up plan MPAVA/64/2015-16 on the approving authority’s portal to confirm the sanction.
The approving body, at scale
Kolar Urban Development Authority
Urban Development AuthorityHas approved 57 RERA projects — 0.7% of Karnataka.
a plotted-layout market — 4% apartments · 96% plotted layouts. Your plotted layout is this body's core business.
- Builders
- 47
- On record
- 0 flats · 5,297 plots
- Reach
- 6 taluks
- Since
- 2017
More layout-heavy than Karnataka overall — 96% plots here vs 38% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
Planning authority — done
Complaints register4 complaints on RERA Karnataka’s register for this project — 8 disposed.
A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.