HORIZONMarkets
Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
18 spaces
Land area
386 sq m
Sanctioned built-up
513 sq m

Timeline

RERA registeredMay 2019
Proposed completionJan 2022
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

TUSHIRAJ REALTECH PRIVATE LIMITED

CompanyPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2019–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kalyan
Taluka
Kalyan
District
Thane
Pincode
421301
Survey no.
2518
North boundary
GHODEKHOT LANE ROAD
East boundary
SHUBHCHINTAN SOCIETY
South boundary
C R M OAK HIGH SCHOOL
West boundary
KDMC SCHOOL
What’s nearby
SchoolsNearest school 1.7km away · College or university 257m away
HealthcareHospital 213m away · 7 clinics within 1km
LifestylePark 1.2km away
ShoppingNo supermarket within 2km · Bank 240m away
Getting around
Expressway 674 m · Kalyan Bhiwandi RoadPrimary road 142 m · Agra RoadRailway line 1.1 kmRailway station 1.1km away (Kalyan Junction)Bus stop within 1km
Water & environment
Water body 520 m · Kala TalaoRiver 1.1 km · Ulhas
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Kalyan Dombivli Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 2518

The promised possession date (31 Jan 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kalyan Dombivli Municipal Corporation

Municipal corporation

Has approved 742 RERA projects3.7% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
585
On record
5,683 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.