Complete project overview

MahaRERA · Registration filing
Floors
9
Buildings
2
Parking
10 spaces
Land area
334 sq m
Sanctioned built-up
1,180 sq m

Timeline

RERA registeredMay 2023
Proposed completionDec 2025
TodayJul 2026
Construction progress
Podiums0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Energy managemcnt0%
Electrical meter r…0%
OC-readiness99%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SAMRUDDHI BUILDCON

PartnershipPromoter type
Thane, MAHARASHTRABased in
4Projects
4Cities
2019–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
181 homeson the public record across 4 projects
16,444 sq mbuilt-up filed
11,929 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kalyan Dombivli Municipal CorporationMunicipal Corporationthis project1 of 3 projects
Nagar Rachna And Mulya Nirdharan Vibhag Thane Branch1 of 3 projects
Nashik Municipal CorporationMunicipal Corporation1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
421202
Survey no.
C.T.S. No. 1428 to 1436 S.No.29 Part
North boundary
GOLKAHE BUNGLOW
East boundary
VASTU SOCIETY
South boundary
Road
West boundary
SADGURU KRUPA SOCIETY
What’s nearby
SchoolsNo schools within 2km · College or university 441m away
HealthcareHospital 177m away · 8 clinics within 1km
LifestylePark 1.1km away
ShoppingNo supermarket within 2km · Bank 433m away
Getting around
Expressway 1.3 km · Chatrapati Shivaji Maharaj Putala ChowkPrimary road 132 m · Agra RoadRailway line 522 mRailway station 502m away (Kalyan Junction)2 bus stops within 500m
Water & environment
Water body 628 m · Kala TalaoRiver 1.7 km · Ulhas
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Kalyan Dombivli Municipal Corporation

Municipal Corporation
Building Permit
Survey no. C.T.S. No. 1428 to 1436 S.No.29 Part

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kalyan Dombivli Municipal Corporation

Municipal corporation

Has approved 742 RERA projects3.7% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
585
On record
5,683 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.