HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
35 spaces
Land area
468 sq m
Sanctioned built-up
1,877 sq m

Timeline

RERA registeredFeb 2024
Proposed completionDec 2028
TodayJul 2026
Construction progress
Podiums0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Open Parking0%
OC-readiness15%
External finishes40%
Stilt floor45%
Flat fit-out45%
Internal finishes55%
Stairs & lifts65%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

VIKAS WAMAN MHATRE

IndividualPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
DOMBIVLI
Taluka
Kalyan
District
Thane
Pincode
421202
Survey no.
PLOT NO 17 NEW SURVEY NO 229/A ,OLD SURVEY NO 326A (PART)
North boundary
VAINKATESH DARSHAN BUILDING
East boundary
STANDALONE CHAUDHARI BUILDING
South boundary
DIGVIJAY SOCIETY
West boundary
ROAD
What’s nearby
SchoolsNo schools within 2km · College or university 441m away
HealthcareHospital 177m away · 8 clinics within 1km
LifestylePark 1.1km away
ShoppingNo supermarket within 2km · Bank 433m away
Getting around
Expressway 1.3 km · Chatrapati Shivaji Maharaj Putala ChowkPrimary road 132 m · Agra RoadRailway line 522 mRailway station 502m away (Kalyan Junction)2 bus stops within 500m
Water & environment
Water body 628 m · Kala TalaoRiver 1.7 km · Ulhas
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Kalyan Dombivli Municipal Corporation

Municipal Corporation
Building Permit
Survey no. PLOT NO 17 NEW SURVEY NO 229/A ,OLD SURVEY NO 326A (PART)
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kalyan Dombivli Municipal Corporation

Municipal corporation

Has approved 742 RERA projects3.7% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
585
On record
5,683 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.