01

Complete project overview

K-RERA · Registration filing
Units
9 units
Mix
9 × Bangalow / Villas
Buildings
9
Land area
1,536 sq m
Floor area
504 sq m
Description
Sophia Avani

Timeline

Project startedJul 2021
RERA registeredJan 2023
Proposed completionNov 2023
TodaySep 2026
Construction progress

88% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the builder's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.

9 of 9 available
TypeArea sq mAvailable
Bangalow / Villas1951 of 1
Bangalow / Villas567 of 7
Bangalow / Villas571 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the builder declared — not a live booking system.

02

Builder’s track record

K-RERA · Builder registration

Joyce George

Ernakulam, KeralaBased in
No — the promoter declared this is a first projectDeclared prior experience
13Projects
1Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
128 homes · 38 plotson the public record across 13 projects
5,870 sq mbuilt-up filed
12,540 sq mplotted area
22,488 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Eloor MuncipalityLocal body (LSGI)4 of 13 projects
Cheranalloor Grama PanchayatGrama Panchayat1 of 13 projects
Chottanikkara Grama PanchayatGrama Panchayat1 of 13 projects
Kochi Municipal CorporationMunicipal Corporation1 of 13 projects
Kottuvally Grama PanchayatGrama Panchayat1 of 13 projects
Thiruvaniyoor Grama PanchayatGrama Panchayatthis project1 of 13 projects
Thrikkakara MuncipalityLocal body (LSGI)1 of 13 projects
Thrikkakara MunicipalityMunicipality1 of 13 projects
Vadavukode Puthencruz Grama PanchayatGrama Panchayat1 of 13 projects
Vengola Grama PanchayatGrama Panchayat1 of 13 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Joyce George— the full portfolio →

03

Location

K-RERA · Registration filing
Street
THIRUVANIYOOR
Village
THIRUVANIYOOR
Taluk
Kunnathunad
District
Ernakulam
Pincode
682312
Survey no.
21/41
Patta no.
8465
What’s nearby
SchoolsNearest school 2.0km away · College or university 1.9km away
HealthcareHospital 172m away
LifestyleNo parks within 2km · 5 restaurants and cafes within 1km
ShoppingSupermarket 275m away · Mall 728m away · Bank 226m away
Getting around
Expressway 2.5 km · Kochi - Madurai - Dhanushkodi RoadPrimary road 3.5 km · Ettumanoor - Ernakulam RoadRailway line 1.8 kmRailway station 1.9km away (Chottanikkara Road)3 bus stops within 500m
Water & environment
Water body 266 m · YakshikulamCanal 840 m
distances only — not a flood assessment
04

Government Guidance Rate

Kerala Registration Department — fair value

In Kerala it’s called the fair value.

₹2,207per sq yd
₹2,640per sq m
Which rate
Residential Plot with Corp./Mun./Panch. road access
Matched to
The value published for this project's own survey number, in “Thiruvaniyur”.

What this number is — and isn’t

  • The minimum value Kerala’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of parcel, and says so above. How Horizon decides what to show.
05

Planning authority

K-RERA · Approved building plan

Thiruvaniyoor Grama Panchayat

Grama Panchayat
approved 13 Jul 2021 · 5 yrs ago
Building Permit no. A3-BA(146114)/2021Survey no. 21/41

The promised possession date (9 Nov 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

Verify it yourself — look up plan A3-BA(146114)/2021 on the approving authority’s portal to confirm the approval.

The approving body, at scale

Grama Panchayat

A village-level local self-government (LSGI) that issues the permit — Kerala's most common approving body. It has approved 268 RERA projects across 13 districts about 1 in 6 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

184 residential projects still under way within 25 km. The nearest 6:

THIRUVANKULAMResidential (Apartment)

VEEGALAND GREEN FORT

VEEGALAND DEVELOPERS PRIVATE LIMITED

Nov 2023registered
Aug 2027target completion
Government Guidance Rate₹4,415/sq ydScale54 flatsAuthorityK-RERA
NADAMAResidential (Apartment)

ASSET DOMINION

ASSET HOMES PRIVATE LIMITED

Feb 2022registered
Mar 2026target completion
Government Guidance Rate₹5,518/sq ydScale78 flatsAuthorityK-RERA
THEKKUMBHAGOM KANAYANNURResidential (Apartment)

VEEGALAND GREEN HEIGHTS

VEEGALAND DEVELOPERS PRIVATE LIMITED

Oct 2023registered
Aug 2028target completion
Scale141 flatsAuthorityK-RERA
THEKKUMBHAGOM KANAYANNURResidential (Apartment)

VEEGALAND SERENE

VEEGALAND DEVELOPERS PRIVATE LIMITED

Dec 2025registered
Mar 2030target completion
Scale58 flatsAuthorityK-RERA
THIRUVANKULAMResidential (Apartment)

LOTUS SIVAGANGA

LOTUS PROPERTIES

Aug 2023registered
Mar 2027target completion
Government Guidance Rate₹7,726/sq ydScale22 flatsAuthorityK-RERA
THEKKUMBHAGOM KANAYANNURResidential (Apartment)

SIDDHI PRANAVAM

SIDDHI HOMES

Dec 2021registered
Aug 2026target completion
Scale49 flatsAuthorityK-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.