Complete project overview

UP-RERA · Registration filing
Project name
sparsh greens
Land area
4,799 sq m

Timeline

Project startedFeb 2012
RERA registeredAug 2017
Proposed completionFeb 2018
TodaySep 2026
02

Builder’s track record

UP-RERA · Builder registration

SPARSH DEVELOPERS

Partnership FirmPromoter type
1Registered projects
2Projects
2Cities
2017–2023Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
49 homeson the public record across 2 projects
27,077 sq mland declared
₹78.97 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from SPARSH DEVELOPERS— the full portfolio →

03

Location & price analysis

UP-RERA · Registration filing
District
Bareilly
Tehsil
Bareilly
Site access
central gate
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 602m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.3 kmPrimary road 775 m · Pilibhit By Pass RoadRailway line 4.7 kmRailway station 4.8km away (Izatnagar Junction)Limited bus connectivity nearby
Water & environment
River 630 m · Nakatia NadiWater body 2.2 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹20.00 Cr declared. What that works out to:

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Uttar Pradesh registration department

In Uttar Pradesh it’s called the circle rate.

No government guidance rate is shown for this project.

Uttar Pradesh's government guidance rates aren't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

UP-RERA · Approved building plan
Building Permit

The promised possession date (5 Feb 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

07

Other projects nearby

The register · within 25 km

11 residential projects still under way within 25 km. Step out ring by ring:

Of the 72 projects the radar draws within 6 km — every kind, every stage — 6 are residential projects still under way. This list keeps only those, and looks further out.

4 projects within 3 km — showing the nearest 4.

430 m awayResidential

PHOOL NARAYAN VILLAS

JANG BAHADUR SINGH; VIDYA DEVI · Bareilly

Jul 2024registered
Jan 2029target completion
no escrow declaredDeclared cost₹15.32 CrAuthorityUP-RERA
780 m awayResidential

GRANDEUR VILLAS

REAL IMAGE DEVELOPERS PVT. LTD. · Bareilly

Jan 2022registered
Nov 2026target completion
no escrow declaredDeclared cost₹61.31 CrAuthorityUP-RERA
1.7 km awayResidential

ROYAL VILLAS

AERA CONSTRUCTION AND DEVELOPERS PVT. LTD.; ARSHAD HASAN KHAN; MASOOD HASAN KHAN; MHOD RAFI · Bareilly

Aug 2020registered
Jul 2027target completion
Declared cost₹21.00 CrAuthorityUP-RERA
2.4 km awayResidential

Golden I Apartment

GOLDEN I INFRASTRUCTURE · Bareilly

Mar 2023registered
Feb 2028target completion
Declared cost₹60.00 CrScale150 flatsAuthorityUP-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.