Complete project overview

GujRERA · Registration filing
Units
373 units
Mix
353 × Flats · 20 × Shops
Carpet area
17–57 sq mper-unit range, as filed
Blocks
7
Parking
756 spaces
Land area
7,845 sq m
Affordable housing
Yes — registered under affordable housingprice caps & eligibility apply

Timeline

Project startedOct 2020
RERA registeredApr 2021
Proposed completionOct 2026
TodayJul 2026
Construction progress

98% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

373 units across 2 batches
TypeArea sq mCount
Flats55353
Shops3120

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

OM DEVELOPERS

PARTNERSHIP FIRMPromoter type
Rajkot, GujaratBased in
72Projects
24Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
4,568 homes · 527 plotson the public record across 72 projects
2,54,826 sq mbuilt-up filed
9,489 sq mplotted area
1,22,506 sq mland declared
₹486.21 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation8 of 48 projects
Othersthis project7 of 48 projects
Bharuch- Ankleshwar Urban Development AuthorityUrban Development Authority5 of 48 projects
Vadodara Municipal CorporationMunicipal / Corporation5 of 48 projects
Surat Municipal CorporationMunicipal / Corporation4 of 48 projects
Gandhinagar Urban Development AuthorityUrban Development Authority3 of 48 projects
Nashik Municipal CorporationMunicipal Corporation3 of 48 projects
Rajkot Municipal CorporationMunicipal / Corporation3 of 48 projects
Ahmedabad Urban Development AuthorityUrban Development Authority2 of 48 projects
Pune Metropolitan Region Development AuthorityMetropolitan Development Authority2 of 48 projects
Bncmc1 of 48 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation1 of 48 projects
Nadiad MunicipalityMunicipal / Corporation1 of 48 projects
Talegaon Dabhade1 of 48 projects
Town Palnning And Collector Office, PalgharCollector office1 of 48 projects
Vaghodia Area Development AuthorityUrban Development Authority1 of 48 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Rajkot
District
Rajkot
Address
80 FEET ROAD, NEAR RAMAPIR CHOWKDIOFF. 150 FEET RING ROAD, RAIYA DHAR
What’s nearby
SchoolsNearest school 2.0km away
HealthcareHospital 632m away · Clinic within 2km
LifestyleNo parks within 2km · Gym or sports centre 1.9km away
ShoppingNo supermarket within 2km
Getting around
Expressway 574 mPrimary road 2.0 kmRailway line 2.3 kmRailway station 4.2km away (Rajkot Junction)Limited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹39.15 Cr declared to build 373 flats. What that works out to:

₹13.00 Lakh – ₹44.31 Lakhdeclared unit pricerange on the filing — not a live asking price
₹10.50 Lakhdeclared cost per flatall-in — land + construction
₹1,806/sq ftof carpet area₹19,437/sq m
30%of the cost is land₹1,379/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Others

Building Permitapproved 27 Apr 2021 · 5 yrs ago
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The approving authority

The body that sanctioned this project. It has approved 2,653 RERA projects across 26 talukas about 1 in 6 in Gujarat.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.