Complete project overview

GujRERA · Registration filing
Units
69 units
Mix
69 × commercial and residential
Carpet area
16–103 sq mper-unit range, as filed
Blocks
2
Parking
3 spaces
Land area
2,319 sq m

Timeline

Project startedOct 2020
RERA registeredFeb 2021
Proposed completionMar 2025
TodayJul 2026
Construction progress

100% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

69 units across 1 batch
TypeArea sq mCount
commercial and residential6669

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

OM DEVELOPERS

PARTNERSHIP FIRMPromoter type
Gandhinagar, GujaratBased in
72Projects
24Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
4,568 homes · 527 plotson the public record across 72 projects
2,54,826 sq mbuilt-up filed
9,489 sq mplotted area
1,22,506 sq mland declared
₹486.21 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation8 of 48 projects
Othersthis project7 of 48 projects
Bharuch- Ankleshwar Urban Development AuthorityUrban Development Authority5 of 48 projects
Vadodara Municipal CorporationMunicipal / Corporation5 of 48 projects
Surat Municipal CorporationMunicipal / Corporation4 of 48 projects
Gandhinagar Urban Development AuthorityUrban Development Authority3 of 48 projects
Nashik Municipal CorporationMunicipal Corporation3 of 48 projects
Rajkot Municipal CorporationMunicipal / Corporation3 of 48 projects
Ahmedabad Urban Development AuthorityUrban Development Authority2 of 48 projects
Pune Metropolitan Region Development AuthorityMetropolitan Development Authority2 of 48 projects
Bncmc1 of 48 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation1 of 48 projects
Nadiad MunicipalityMunicipal / Corporation1 of 48 projects
Talegaon Dabhade1 of 48 projects
Town Palnning And Collector Office, PalgharCollector office1 of 48 projects
Vaghodia Area Development AuthorityUrban Development Authority1 of 48 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Gandhinagar
District
Gandhinagar
Address
FP 66 NEAR DIYA GREEN PARTY PLOTBH. AKSHAR VILLA BUNGALOWS VAVOL UVARSAD ROAD, NEW VAVOL
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.9km away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.8 kmPrimary road 1.1 kmRailway line 779 mRailway station 2.4km away (Gandhinagar Capital)Limited bus connectivity nearby
Water & environment
Water body 1.2 km · Vavol Lake
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹10.30 Cr declared to build 69 flats. What that works out to:

₹5.00 Lakh – ₹27.00 Lakhdeclared unit pricerange on the filing — not a live asking price
₹14.93 Lakhdeclared cost per flatall-in — land + construction
₹2,096/sq ftof carpet area₹22,557/sq m
11%of the cost is land₹434/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Others

Building Permitapproved 8 Feb 2021 · 5 yrs ago

The promised possession date (31 Mar 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Building-Use (BU) permission — the occupancy sign-off, on record

All 2 blocks carry a Building-Use (BU) permission (latest 29 Nov 2022)— Gujarat’s legal-to-occupy sign-off, and the completion proof most RERA records simply don’t carry. Still confirm the BU covers your specific unit before you rely on it.

The approving body, at scale

The approving authority

The body that sanctioned this project. It has approved 2,653 RERA projects across 26 talukas about 1 in 6 in Gujarat.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.