Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
34 spaces
Land area
746 sq m
Sanctioned built-up
2,246 sq m

Timeline

RERA registeredMar 2025
Proposed completionDec 2030
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Water conservation…0%
Open Parking0%
Internal finishes12%
Stairs & lifts59%
Superstructure62%
Plinth95%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

OM DEVELOPERS

PartnershipPromoter type
Nashik, MAHARASHTRABased in
72Projects
24Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
4,568 homes · 527 plotson the public record across 72 projects
2,54,826 sq mbuilt-up filed
9,489 sq mplotted area
1,22,506 sq mland declared
₹486.21 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation8 of 48 projects
Others7 of 48 projects
Bharuch- Ankleshwar Urban Development AuthorityUrban Development Authority5 of 48 projects
Vadodara Municipal CorporationMunicipal / Corporation5 of 48 projects
Surat Municipal CorporationMunicipal / Corporation4 of 48 projects
Gandhinagar Urban Development AuthorityUrban Development Authority3 of 48 projects
Nashik Municipal CorporationMunicipal Corporation3 of 48 projects
Rajkot Municipal CorporationMunicipal / Corporation3 of 48 projects
Ahmedabad Urban Development AuthorityUrban Development Authority2 of 48 projects
Pune Metropolitan Region Development AuthorityMetropolitan Development Authority2 of 48 projects
Bncmc1 of 48 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation1 of 48 projects
Nadiad MunicipalityMunicipal / Corporation1 of 48 projects
Talegaon Dabhade1 of 48 projects
Town Palnning And Collector Office, PalgharCollector office1 of 48 projects
Vaghodia Area Development AuthorityUrban Development Authority1 of 48 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nashik (M Corp.)
Taluka
Nashik
District
Nashik
Pincode
422006
Survey no.
PLOT NO. 56 SURVEY NO.9/1/A2+9/1B AGARTAKLI NASHIK
North boundary
PLOT NO 56 PART SURVEY NO 9
East boundary
9 METER ROAD AND PLOT NO 32
South boundary
ADJ SURVEY NO 9
West boundary
ADJ SURVEY NO 9
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 899m away · 1 clinic within 1km
LifestylePark 1.6km away
ShoppingNo supermarket within 2km
Getting around
Expressway 1.1 kmPrimary road 58 m · Ramdas Swami MargRailway line 3.7 kmRailway station 4.8km away (Nashik Road)Limited bus connectivity nearby
Water & environment
River 360 m · Nasardi
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.