HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
22
Buildings
6
Parking
460 spaces
Land area
8,153 sq m
Sanctioned built-up
38,222 sq m
Recreational open space
251 sq m

Timeline

RERA registeredMay 2022
Proposed completionJun 2026
TodayJul 2026
Construction progress
Stilt floor0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Electrical meter r…0%
Aggregate area of …0%
OC-readiness50%
Fire protection an…50%
Flat fit-out55%
Stairs & lifts85%
External finishes96%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Superstructure100%
Internal finishes100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Akanksha Builders

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2022–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Wakad
Taluka
Mulshi
District
Pune
Pincode
411057
Survey no.
S.No.65/1/1B, 70/1
North boundary
ADJ S No - 71
East boundary
ADJ S No - 70 Part
South boundary
ADJ S No - 65 Part
West boundary
ADJ Hinjawadi Shiv
What’s nearby
Schools1 school within 1km · College or university 1.3km away · Library 1.4km away
HealthcareHospital 466m away · 4 clinics within 1km · Pharmacy within 1km
LifestylePark 1.2km away · Gym or sports centre 1.0km away · 28+ restaurants and cafes within 1km
ShoppingSupermarket 376m away · Mall 359m away · Bank 627m away
Getting around
Expressway 964 m · Mumbai - Satara HighwayPrimary road 22 m · Hinjawadi RoadMetro station 169m away (Jakat Naka)5 bus stops within 500m
Water & environment
River 1.2 km · Mula
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. S.No.65/1/1B, 70/1

The promised possession date (20 Jun 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 0 disposed, 1 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.