Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
207 units across 4 batches
TypeArea sq mCount
1 BHK454
2 BHK4685
2 BHK4916
2 BHK58102
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
Complete project overview — done
02
Builder’s track record
MahaRERA · Builder registration
Wadhwa Construction and Infrastructure Private Limited
3,318 homes · 509 plotson the public record across 28 projects
2,57,652 sq mbuilt-up filed
1,63,402 sq mplotted area
2,17,129 sq mland declared
These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Expressway 2.7 kmPrimary road 4.8 kmRailway line 1.6 km · Panvel Junction - Karjat JunctionRailway station 2.3km away (Mohope)Limited bus connectivity nearby
Water & environment
Water body 342 mRiver 3.7 km
distances only — not a flood assessment
Location — done
04
Government Guidance Rate
Maharashtra IGR — Annual Statement of Rates
In Maharashtra it’s called the ready reckoner rate.
₹26,505per sq yd
₹31,700per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “Wardoli”.
In force
2026-2027 schedule
Spread
₹23,830 – ₹28,177 per sq yd across the places it was taken over
What this number is — and isn’t
The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
Not a market price. Sales normally register above it, and how far above varies by place and by project.
Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
Government Guidance Rate — done
05
Complaints & litigation
MahaRERA · public record
Complaints before MahaRERA
MahaRERA's own register
2 complaints · 1 disposed · 0 open · 1 with no clear status
A disposed complaint may have been resolved for or against the builder, and only disputes escalated to MahaRERA appear here at all.
Number
Date
Status
CC12503707
18 Oct 2025
not stated
CC006000000334085
30 Jan 2023
Order Approveddisposed
What the builder declared
Declared to MahaRERA
Litigation
None declared to MahaRERA
The builder's own declaration at registration — not a court's or MahaRERA's finding. A flagged line is worth checking with MahaRERA.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with MahaRERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
06
Other projects nearby
The register · within 25 km
1,654 residential projects still under way within 25 km. Step out ring by ring:
Of the 139 projects the radar draws within 6 km — every kind, every stage — 73 are residential projects still under way. This list keeps only those, and looks further out.
19 projects within 1 km — showing the nearest 6.
40 m awayResidential / Group Housing
Wise City, South Block Phase I, Plot Rz8 Building 3 Wing C1
Wadhwa Construction and Infrastructure Private Limited · Wardoli · Panvel
8 yr 7 mo
May 2018registered
Dec 2026target completion
Government Guidance Rate₹26,505/sq ydScale208 flatsAuthorityMahaRERA