HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
26
Buildings
2
Land area
559 sq m
Sanctioned built-up
3,257 sq m

Timeline

RERA registeredMay 2019
Proposed completionDec 2026
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Community Building…0%
Open Parking0%
Energy managemcnt44%
Fire protection an…80%
Landscaping & Tree…91%
Solid Waste Manage…97%
Sewerage (Chamber,…98%
Treatment And Disp…98%
Internal Roads & F…99%
Storm Water Drains99%
Street Lighting99%
Water conservation…99%
Electrical meter r…99%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Water Supply100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Wadhwa Construction and Infrastructure Private Limited

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
28Projects
1City
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,586 homes · 509 plotson the public record across 28 projects
2,57,652 sq mbuilt-up filed
1,63,402 sq mplotted area
2,17,129 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Wardoli
Taluka
Panvel
District
Raigarh
Pincode
410206
Survey no.
1286, 1288
North boundary
36 M wide DP road
East boundary
Future development
South boundary
layout boundary Plot RZ8 building 1 wing A2
West boundary
36 M wide DP road
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingSupermarket 82m away
Getting around
Expressway 2.6 kmPrimary road 4.6 kmRailway line 1.6 km · Panvel Junction - Karjat JunctionRailway station 2.4km away (Mohope)Limited bus connectivity nearby
Water & environment
Water body 375 mRiver 3.4 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

City and Industrial Development Corporation (CIDCO)

Development Authority
Building Permit
Survey no. 1286, 1288
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

City and Industrial Development Corporation (CIDCO)

Metropolitan / development authority

Has approved 885 RERA projectsabout 1 in 23 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
724
On record
7,061 flats · 987 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

3 complaints on MahaRERA’s register for this project 2 disposed, 1 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.