Complete project overview
MahaRERA · Registration filing- Floors
- 27
- Buildings
- 2
- Land area
- 567 sq m
- Sanctioned built-up
- 12,713 sq m
Timeline
RERA registeredMay 2018
Proposed completionDec 2026
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Podiums0%
Stilt floor0%
Community Building…0%
Open Parking0%
Energy managemcnt35%
Fire protection an…80%
Street Lighting90%
Landscaping & Tree…93%
OC-readiness97%
Solid Waste Manage…97%
Stairs & lifts98%
Sewerage (Chamber,…98%
Treatment And Disp…98%
Internal Roads & F…99%
Water Supply99%
Storm Water Drains99%
Water conservation…99%
Electrical meter r…99%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
External finishes100%
02
Builder’s track record
MahaRERA · Promoter registrationWadhwa Construction and Infrastructure Private Limited
CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
28Projects
1City
2018–presentActive
Timelineevery project, start → promised completion
Wise City, South Block Phase I, Plot RZ8 Building 1 Wing A1Wise City, South Block Phase I, Plot RZ8 Building 4 Wing F4Wise City, South Block Phase I, Plot RZ8 Building 4 Wing F3Wise City, South Block Phase I, Plot RZ8 Building 5 Wing D1Wise City, South Block Phase I, Plot RZ8 Building 2 Wing B3Wise City, South Block Phase I, Plot RZ8 Building 5 Wing D2Wise City, South Block Phase I, Plot Rz8 Building 3 Wing C1Wise City, South Block Phase I, Plot RZ8, Building 3 Wing C2Wise City, South Block Phase I, Plot RZ8 Building 5 Wing D3Wise City, South Block Phase I, Plot RZ8, Building 5 Wing D4Wise City,South Block Phase I, Plot RZ8 Building 6 Wing A4Wise City, South Block Phase I, Plot RZ8, Building 3 Wing C3wise city, south Block, Phase I, Plot RZ8 Building 1 wing A3Wise City, South Block, Phase I,Plot RZ8 Building 4 Wing F2Magnolia Cluster 1Magnolia Cluster 2Magnolia Cluster 3Magnolia Cluster 4Wise City RZ-02 Plotted DevelopmentWise City RZ-03 Plotted DevelopmentWise City RZ8 Wing E2Wise City RZ8 Wing B1Wise City RZ-01 Plotted Development - Phase 2Wise City RZ-01 Plotted Development - Phase 3Wise City RZ-01 Plotted Development - Phase 1Wise City RZ8 Wing A2Wise City CZ-05 Retail BuildingWise City RZ8 Wing D5
Builder DNAthe whole portfolio, summed
1,586 homes · 509 plotson the public record across 28 projects
2,57,652 sq mbuilt-up filed
1,63,402 sq mplotted area
2,17,129 sq mland declared
These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- Wardoli
- Taluka
- Panvel
- District
- Raigarh
- Pincode
- 410206
- Survey no.
- Survey No. 117/18, 117/16
- North boundary
- Plot RZ9 Building 1 Wing D1
- East boundary
- Layout Boundary
- South boundary
- Plot RZ9 Building 1 Wing D3
- West boundary
- Future Development
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingSupermarket 347m away
Getting around
Expressway 2.9 kmRailway line 1.7 km · Panvel Junction - Karjat JunctionRailway station 2.4km away (Mohope)Limited bus connectivity nearby
Water & environment
Water body 289 mRiver 3.8 km
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
Compliance1 non-compliance notice on record
5 complaints on MahaRERA’s register for this project — 4 disposed, 1 still open.
A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.