HORIZON
Share

Ariha One08

P51800078835 · MahaRERA · https://gethorizon.in/projects/ariha-one08-pahadi-goregaon-borivali-sh0ykli1

01

Complete project overview

MahaRERA · Registration filing
Units
18 units
Floors
23
Buildings
2
Parking
40 spaces
Land area
736 sq m
Sanctioned built-up
3,972 sq m

Timeline

RERA registeredJan 2025
Proposed completionDec 2027
TodaySep 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Flat fit-out2%
Internal finishes15%
Superstructure72%
Excavation100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

ARIHA SPACES LLP

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pahadi-Goregaon
Taluka
Borivali
District
Mumbai Suburban
Pincode
400104
Survey no.
PLOT NO 131 BEARING CTS NO 671 671 (1 TO 11))
North boundary
PLOT NO 130
East boundary
BUILDING NO 9
South boundary
PLOT NO 132
West boundary
ROAD NO 1
What’s nearby
Schools4 schools within 1km · 4 educational institutions within 1km · College or university 1.8km away
HealthcareHospital 71m away · 10 clinics within 1km · Doctor's clinic within 1km
Lifestyle1 park within 500m · 9 restaurants and cafes within 1km
ShoppingSupermarket 681m away · Mall 138m away · Bank 349m away
Getting around
Expressway 1.3 kmPrimary road 1 m · Swami Vivekanand RoadRailway line 381 m · Central Railway (Harbour Line)Railway station 411m away (Goregaon)Bus stop within 500m
Water & environment
River 690 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Slum Rehabilitation Authority

Slum Rehabilitation Authority
Building Permit
Survey no. PLOT NO 131 BEARING CTS NO 671 671 (1 TO 11))
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Slum Rehabilitation Authority

Planning authority

Has approved 729 RERA projects3.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
554
On record
15,389 flats · 0 plots
Reach
4 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,805 residential projects still under way within 25 km. Step out ring by ring:

Of the 2,072 projects the radar draws within 6 km — every kind, every stage — 695 are residential projects still under way. This list keeps only those, and looks further out.

63 projects within 1 km — showing the nearest 6.

10 m awayOthers

ASHWIN HEIGHTS

WESTINRELY DEVELOPERS PVT LTD · Pahadi-Goregaon · Borivali

May 2024registered
Dec 2026target completion
Scale37 flatsAuthorityMahaRERA
10 m awayOthers

ARIHA VINCERE

VELSTAND REALTY LLP · Pahadi-Goregaon · Borivali

Jul 2024registered
Jun 2027target completion
Government Guidance Rate₹1,34,466/sq ydScale95 flatsAuthorityMahaRERA
10 m awayOthers

Opulence

ARIHA BUILDTECH LLP · Pahadi-Goregaon · Borivali

Oct 2024registered
Dec 2029target completion
Government Guidance Rate₹1,34,466/sq ydScale1,004 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

STUVI RESIDENCY

STUVI REALITY LLP · Pahadi-Goregaon · Borivali

May 2026registered
Dec 2027target completion
Scale12 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

Integrated Ramicon A

Integrated Affordable Home Private Limited · Goregaon · Borivali

May 2024registered
Dec 2027target completion
Government Guidance Rate₹1,54,065/sq ydScale105 flatsAuthorityMahaRERA
60 m awayMixed

PARAS GOREGAON CO-OP HSG SOC LTD

Madhav Enterprise · Goregaon · Borivali

Sep 2025registered
Dec 2028target completion
Government Guidance Rate₹1,44,742/sq ydScale18 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.