ASOPALAV PRIME

PR/GJ/RAJKOT/RAJKOT/Others/CAA08001/030221 · GujRERA · https://gethorizon.in/projects/asopalav-prime-rajkot-06o5bzot

01

Complete project overview

GujRERA · Registration filing
Project name
ASOPALAV PRIME
Units
51 units
Mix
51 × Offices
Carpet area
13–37 sq mper-unit range, as filed
Parking
75 spaces
Land area
585 sq m

Timeline

Project startedNov 2020
RERA registeredFeb 2021
Proposed completionMay 2023
TodaySep 2026
Construction progress

100% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your unit

Filed by type and size, in the batches the builder registered — not a per-unit listing. Look yours up.

51 units across 1 batch
TypeArea sq mCount
Offices2251

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Builder registration

LANDMARK NETWORK

PARTNERSHIP FIRMPromoter type
Rajkot, GujaratBased in
4Projects
1City
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
394 homeson the public record across 4 projects
12,890 sq mbuilt-up filed
5,797 sq mland declared
₹36.04 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Othersthis project3 of 4 projects
Rajkot Municipal CorporationMunicipal / Corporation1 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from LANDMARK NETWORK— the full portfolio →

03

Location & price analysis

GujRERA · Registration filing
Taluka
Rajkot
District
Rajkot
Address
ASOPALAV PRIME,NEAR MATUKI RESTAURANT40 FEET ROAD
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 899m away · 1 clinic within 1km
LifestylePark 756m away
ShoppingNo supermarket within 2km · Mall 923m away
Getting around
Expressway 1.3 kmPrimary road 2.9 km · AG Chowk FlyoverRailway line 2.6 km · Rajkot–SomnathRailway station 3.5km away (Bhaktinagar)Bus stop within 1km
Water & environment
Water body 3.1 km · Water TankRiver 3.3 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹3.70 Cr declared to build 51 flats. What that works out to:

₹3.65 Lakh – ₹24.00 Lakhdeclared unit pricerange on the filing — not a live asking price
₹7.25 Lakhdeclared cost per flatall-in — land + construction
₹3,001/sq ftof carpet area₹32,298/sq m
9%of the cost is land₹550/sq ft of land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Gujarat registration department

In Gujarat it’s called the jantri rate — the 2011 book, which is the one in Horizon's record.

No government guidance rate is shown for this project.

Gujarat's jantri is in Horizon's record, but this filing names no place the book prints — or names two — and a survey number repeats in every village of a district, so nothing can be tied to this project without guessing.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

GujRERA · Approved building plan

Others

Building Permitapproved 3 Feb 2021 · 5 yrs ago

The promised possession date (21 May 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Building-Use (BU) permission — the occupancy sign-off, on record

All 1 block carry a Building-Use (BU) permission (latest 6 May 2022)— Gujarat’s legal-to-occupy sign-off, and the completion proof most RERA records simply don’t carry. Still confirm the BU covers your specific unit before you rely on it.

The approving body, at scale

The approving authority

The body that approved this project. It has approved 2,653 RERA projects across 26 talukas about 1 in 6 in Gujarat.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

112 commercial projects still under way within 25 km. Step out ring by ring:

Of the 1,314 projects the radar draws within 6 km — every kind, every stage — 87 are commercial projects still under way. This list keeps only those, and looks further out.

3 projects within 1 km — showing the nearest 3.

610 m awayCommercial

SONAMAHOR.COMM

SHIV CON · Rajkot

Nov 2024registered
Dec 2028target completion
Price band₹3.50 Lakh–₹25.46 LakhScale47 flatsAuthorityGujRERA
770 m awayCommercial

SHYAMAL SANSKRUTI

SHYAMAL SANSKRUTI ENTERPRISE · Rajkot

Jul 2024registered
Dec 2027target completion
Price band₹4.50 Lakh–₹30.00 LakhScale61 flatsAuthorityGujRERA
790 m awayCommercial

SHREEJI CENTER

SHREEJI CENTER · Rajkot

May 2026registered
Dec 2028target completion
Price band₹18.00 Lakh–₹59.50 LakhScale30 flatsAuthorityGujRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.