01
Complete project overview
RERA Telangana · Registration filing- Units
- 99 units
- Unit mix
- 63 × 2BHK, 36 × 3BHK
- Saleable area
- 132–223 sq mper unit, as filed
- Floors
- 9
- Land area
- 4,555 sq m
- Built-up area
- 17,944 sq m
- Road widening
- 124 sq mland set aside for road widening
Timeline
Proposed completionJul 2025
Construction progress92% overall, as filed
Flat fit-out80%
Stairs & lifts80%
External finishes80%
OC-readiness80%
Excavation100%
Basement & plinth100%
Podiums100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block. BuildingFloorTypeArea sq mAvailable
CSR 9912BHK1501 of 1
CSR 9913BHK2231 of 1
CSR 9912BHK1323 of 3
CSR 9913BHK1831 of 1
CSR 9912BHK1361 of 1
CSR 9913BHK1721 of 1
CSR 9912BHKmortgaged1332 of 2
CSR 9913BHK2221 of 1
CSR 9923BHKmortgaged1721 of 1
CSR 9922BHKmortgaged1501 of 1
CSR 9923BHKmortgaged2231 of 1
CSR 9922BHKmortgaged1323 of 3
CSR 9923BHKmortgaged1831 of 1
CSR 9922BHKmortgaged1361 of 1
CSR 9923BHKmortgaged2221 of 1
CSR 9922BHKmortgaged1332 of 2
CSR 9933BHK2221 of 1
CSR 9932BHK1332 of 2
CSR 9933BHK1721 of 1
CSR 9932BHK1491 of 1
CSR 9933BHK2231 of 1
CSR 9932BHK1323 of 3
CSR 9933BHK1831 of 1
CSR 9932BHK1361 of 1
CSR 9943BHK2221 of 1
CSR 9942BHK1332 of 2
CSR 9943BHK1721 of 1
CSR 9942BHK1501 of 1
CSR 9943BHK2231 of 1
CSR 9942BHK1323 of 3
CSR 9943BHK1831 of 1
CSR 9942BHK1361 of 1
CSR 9953BHK2221 of 1
CSR 9952BHK1332 of 2
CSR 9953BHK1721 of 1
CSR 9952BHK1501 of 1
CSR 9953BHK2231 of 1
CSR 9952BHK1323 of 3
CSR 9953BHK1831 of 1
CSR 9952BHK1361 of 1
CSR 9963BHK2221 of 1
CSR 9962BHK1332 of 2
CSR 9963BHK1721 of 1
CSR 9962BHK1501 of 1
CSR 9963BHK2231 of 1
CSR 9962BHK1323 of 3
CSR 9963BHK1831 of 1
CSR 9962BHK1361 of 1
CSR 9973BHK2221 of 1
CSR 9972BHK1332 of 2
CSR 9973BHK1721 of 1
CSR 9972BHK1501 of 1
CSR 9973BHK2231 of 1
CSR 9972BHK1323 of 3
CSR 9973BHK1831 of 1
CSR 9972BHK1361 of 1
CSR 9983BHK2221 of 1
CSR 9982BHK1332 of 2
CSR 9983BHK1721 of 1
CSR 9982BHK1501 of 1
CSR 9983BHK2231 of 1
CSR 9982BHK1323 of 3
CSR 9983BHK1831 of 1
CSR 9982BHK1361 of 1
CSR 9993BHK2221 of 1
CSR 9992BHK1332 of 2
CSR 9993BHK1721 of 1
CSR 9992BHK1501 of 1
CSR 9993BHK2231 of 1
CSR 9992BHK1323 of 3
CSR 9993BHK1831 of 1
CSR 9992BHK1361 of 1
Complete project overview — done
02
Builder’s track record
RERA Telangana · Promoter registrationM/s MIHIRA BUILDCON
PartnershipPromoter type
Warangal Urban, TelanganaBased in
1Projects
1City
2019–2025Active
Timelineevery project, start → promised completion
20192020202120222023202420252026today
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Builder's track record — done
03
Location
RERA Telangana · Registration filing- Locality
- HANAMKONDA`
- Mandal
- Hanamkonda
- District
- Warangal Urban
- Pincode
- 506001
- North boundary
- HNO 1 1 27 19 4 C AND OTHERS PLOT
- East boundary
- HOUSE AND LAND OF C SHAILAJA AND RAMESHWAR REDDY
- South boundary
- 60 FEET ROAD
- West boundary
- 30 FEET ROAD
What’s nearbySchools2 schools within 500m · 10 educational institutions within 1km · College or university 469m away
HealthcareHospital 110m away · 3 clinics within 1km · Pharmacy within 1km
LifestylePark 911m away · Gym or sports centre 1.4km away · 12+ restaurants and cafes within 1km
ShoppingSupermarket 831m away · Mall 353m away · Bank 369m away
Getting aroundExpressway 65 mPrimary road 3 mRailway line 3.5 kmRailway station 4.8km away (Komatipalli)Bus stop within 1km
Water & environmentCanal 781 mWater body 1.3 km · Pochamma Kunta
distances only — not a flood assessment Declared external developmentSewage80%
Sewerage (Chamber,…80%
Rainwater80%
Fire safety60%
Community Building…50%
Electricity50%
Water supply50%
Solid waste0%
Rainwater0%
Renewable energy0%
Aggregate area of …0%
Roads0%
Green Strip/TOT LO…0%
Street lighting0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot. Location — done
04
Planning authority
RERA Telangana · Approved building planBuilding Permit
Survey no. 539/A,540,541,543,550&620
The promised possession date (22 Jul 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t hereA sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
Planning authority — done
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.