01

Complete project overview

MahaRERA · Registration filing
Project name
D SOLITAIRE
Units
135 units
Floors
9
Buildings
2
Parking
1 spaces
Land area
1,266 sq m
Sanctioned built-up
5,450 sq m
Recreational open space
101 sq m

Timeline

RERA registeredNov 2021
Proposed completionMar 2023
TodaySep 2026
Construction progress
Podiums0%
Stilt floor0%
OC-readiness0%
Water Supply0%
Storm Water Drains0%
Solid Waste Manage…0%
Water conservation…0%
Electrical meter r…0%
Sewerage (Chamber,…50%
Flat fit-out65%
External finishes80%
Internal finishes85%
Superstructure87%
Stairs & lifts95%
Excavation100%
Basement (if any)100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

KRISHNAN AND KAMAL ASSOCIATES

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2021–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Borivali
Taluka
Borivali
District
Mumbai Suburban
Pincode
400029
Survey no.
1775 TO 1791 B
North boundary
CTS NO 1750 1757 A OF VILLAGE KOLEKALYAN
East boundary
NATIVE ENTRANTY OF VILLAGE KOLEKALYAN
South boundary
CTS NO 1791 C 1791 D OF VILLAGE KOLEKALYAN
West boundary
CTS NO 1792 PT
What’s nearby
SchoolsNo schools within 2km · College or university 1.8km away
HealthcareHospital 1.9km away · 3 clinics within 1km
LifestylePark 580m away
ShoppingNo supermarket within 2km
Getting around
Expressway 1.9 kmPrimary road 1.7 km · Jogeshwari Vikhroli Link RoadRailway line 2.5 kmMetro station 2.0km away (Goregaon (East))Limited bus connectivity nearby
Water & environment
Water body 927 m · Chota Kashmir Lake
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Slum Rehabilitation Authority

Slum Rehabilitation Authority
Building Permit
Survey no. 1775 TO 1791 B

The promised possession date (1 Mar 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Slum Rehabilitation Authority

Planning authority

Has approved 729 RERA projects3.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
554
On record
15,389 flats · 0 plots
Reach
4 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

4,175 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,996 projects the radar draws within 6 km — every kind, every stage — 665 are residential projects still under way. This list keeps only those, and looks further out.

25 projects within 1 km — showing the nearest 6.

10 m awayResidential / Group Housing

Transcon Triumph Tower 3

Transcon Triumph Phase 2 Private Limited · Andheri

Aug 2021registered
Sep 2026target completion
Scale316 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

CODENAME RARE BY RUNWAL

Runwal Developers Ltd · Andheri

Apr 2022registered
Jun 2026target completion
Scale68 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

SENROOFS PHASE - III

PIONEER HOUSING · Kurla

Dec 2021registered
Dec 2027target completion
Scale380 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

THE SANCTUARY - TOWER 2

Runwal Construction Private Limited · Kurla

Jan 2022registered
Mar 2027target completion
AuthorityMahaRERA
10 m awayResidential / Group Housing

INA APARTMENT CO-OPERATIVE HOUSING SOCIETY LIMITED

YASH REALTORS · Borivali

Feb 2022registered
Dec 2026target completion
Scale16 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

Avyukta Neelkamal

Shivoham Associates · Borivali

May 2022registered
Sep 2026target completion
1 open complaintScale151 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.