HORIZON
Share

EMPIRE PRESIDENCY

P51700046747 · MahaRERA · https://gethorizon.in/projects/empire-presidency-thane-m-corp-7ro7a80w

01

Complete project overview

MahaRERA · Registration filing
Units
46 units
Floors
8
Buildings
2
Parking
79 spaces
Land area
900 sq m
Sanctioned built-up
3,023 sq m

Timeline

RERA registeredSep 2022
Proposed completionJul 2025
TodaySep 2026
Construction progress
Podiums0%
Internal finishes0%
Flat fit-out0%
Internal Roads & F…0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
External finishes10%
OC-readiness10%
Stairs & lifts30%
Water Supply50%
Water conservation…50%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

LAKHANI BUILDERS PVT LTD

CompanyPromoter type
Thane, MAHARASHTRABased in
10Projects
3Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
744 homeson the public record across 10 projects
52,109 sq mbuilt-up filed
23,207 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Tmcthis project3 of 5 projects
City and Industrial Development Corporation (CIDCO)Development Authority1 of 5 projects
Panvel Municipal CorporationMunicipal Corporation1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from LAKHANI BUILDERS PVT LTD— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400602
Survey no.
F.P NO. 294
North boundary
FP NO 298
East boundary
ROAD
South boundary
ROAD
West boundary
FP NO 295
What’s nearby
Schools1 school within 1km · College or university 1.5km away · Library 1.1km away
HealthcareHospital 208m away · 8 clinics within 1km · Pharmacy within 1km
LifestylePark 1.1km away · Gym or sports centre 345m away · 16+ restaurants and cafes within 1km
ShoppingSupermarket 808m away · Mall 1.7km away · Bank 48m away
Getting around
Expressway 207 mPrimary road 526 m · Lal Bahadur Shastri MargRailway line 1.3 kmMetro station 852m away (Teen Hath Naka Station)9 bus stops within 500m
Water & environment
Water body 495 m · Kacharali Lake
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹60,034per sq yd
₹71,800per sq m
Which rate
residential flat (built)
Matched to
The middle rate across the 101 divisions of “Thane (M Corp.)” — the city's middle, not this project's own division.
In force
2026-2027 schedule
Spread
₹26,923₹1,55,185 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of city, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Tmc

Building Permit
Survey no. F.P NO. 294

The promised possession date (31 Jul 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Tmc

Planning authority

Has approved 42 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
24
On record
1,831 flats · 0 plots
Reach
2 districts
Since
2019

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

4,853 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,562 projects the radar draws within 6 km — every kind, every stage — 535 are residential projects still under way. This list keeps only those, and looks further out.

76 projects within 1 km — showing the nearest 6.

70 m awayOthers

Thane Shivam Chs Ltd

Mahesh Shriram Borkar · Thane

Dec 2022registered
Dec 2026target completion
Government Guidance Rate₹60,034/sq ydScale37 flatsAuthorityMahaRERA
100 m awayResidential / Group Housing

EMPIRE HERITAGE

LAKHANI BUILDERS PVT LTD · Thane

Aug 2022registered
Jul 2027target completion
Government Guidance Rate₹60,034/sq ydAuthorityMahaRERA
100 m awayResidential / Group Housing

EMPIRE DYNASTY

LAKHANI BUILDERS PVT LTD · Thane

Sep 2023registered
Dec 2030target completion
Government Guidance Rate₹60,034/sq ydScale257 flatsAuthorityMahaRERA
200 m awayResidential / Group Housing

Stellar

Trimity Realty LLP · Thane

Jan 2023registered
Dec 2027target completion
Government Guidance Rate₹60,034/sq ydScale668 flatsAuthorityMahaRERA
200 m awayResidential / Group Housing

Dream Pragati

Empire Horizons Private Limited · Thane

Aug 2025registered
Dec 2028target completion
Government Guidance Rate₹60,034/sq ydScale71 flatsAuthorityMahaRERA
200 m awayResidential / Group Housing

Anupam Chs. Ltd.

Shree Mangalmurti Enterprises · Thane

Nov 2025registered
Dec 2029target completion
Government Guidance Rate₹60,034/sq ydScale51 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.