Complete project overview

MahaRERA · Registration filing
Floors
10
Parking
111 spaces
Land area
4,419 sq m
Sanctioned built-up
15,659 sq m

Timeline

RERA registeredJan 2022
Proposed completionDec 2024
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

Laaman Developers

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2022–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400604
Survey no.
Plot No. C-9
North boundary
12 Mtr Wide Road
East boundary
Plot No PL -6 Encrachment
South boundary
Encroachment
West boundary
Open Space -9
What’s nearby
Schools1 school within 1km · College or university 1.7km away · Library 1.6km away
HealthcareHospital 370m away · Clinic within 2km · Pharmacy within 1km
LifestylePark 1.7km away · Playground within 500m · Gym or sports centre 644m away
ShoppingSupermarket 1.3km away · Mall 1.3km away · Bank 439m away
Getting around
Expressway 544 mPrimary road 944 m · Lal Bahadur Shastri MargRailway line 1.7 kmMetro station 954m away (Teen Hath Naka Station)11 bus stops within 500m
Water & environment
Water body 531 m · Rayladevi Lake
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Maharashtra Industrial Development Corporation (MIDC)

Development Authority
Building Permit
Survey no. Plot No. C-9

The promised possession date (31 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra Industrial Development Corporation (MIDC)

Metropolitan / development authority

Has approved 156 RERA projects0.8% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
118
On record
3,504 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.