Units
406 units
Floors
16
Buildings
8
Parking
832 spaces
Land area
11,090 sq m
Sanctioned built-up
38,940 sq m

Timeline

RERA registeredMar 2023
Proposed completionDec 2026
TodaySep 2026
Construction progress
Podiums0%
Stilt floor0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Open Parking0%
Flat fit-out50%
External finishes50%
OC-readiness50%
Internal finishes85%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Stairs & lifts100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

MERLIN BHINGARWALA DEVELOPERS LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
2Projects
2Cities
2023–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
661 homeson the public record across 2 projects
75,246 sq mbuilt-up filed
15,468 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pimpri Chinchwad Municipal CorporationMunicipal Corporationthis project1 of 2 projects
Pune Municipal CorporationMunicipal Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from MERLIN BHINGARWALA DEVELOPERS LLP— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Tathwade
Taluka
Mulshi
District
Pune
Pincode
411033
Survey no.
55/1A/1/11 TO 55/1A/1/14
North boundary
Survey no 56-2 and partly by survey no 58
East boundary
partly Survey no 55-1 and partly by survey no 56-2
South boundary
Internal road
West boundary
24 meter DP road
What’s nearby
Schools1 school within 500m · 3 educational institutions within 1km
HealthcareHospital 1.2km away · Clinic within 2km · Pharmacy within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.3km away · 22+ restaurants and cafes within 1km
ShoppingSupermarket 1.2km away · Mall 1.4km away
Getting around
Expressway 384 mPrimary road 267 m · Service RoadRailway line 4.1 km · Mumbai–Pune RailwayMetro station 2.4km away (Jakat Naka)2 bus stops within 500m
Water & environment
Water body 285 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹58,805per sq yd
₹70,330per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “Tathwade”.
In force
2026-2027 schedule
Spread
₹38,537₹71,715 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 55/1A/1/11 TO 55/1A/1/14
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,150 residential projects still under way within 25 km. Step out ring by ring:

Of the 2,093 projects the radar draws within 6 km — every kind, every stage — 706 are residential projects still under way. This list keeps only those, and looks further out.

21 projects within 1 km — showing the nearest 6.

310 m awayOthers

Metro Life Ultima Residences Phase I

Rama Synergy Spaces · Tathwade · Mulshi

Jun 2023registered
Dec 2027target completion
Government Guidance Rate₹58,805/sq ydScale194 flatsAuthorityMahaRERA
520 m awayResidential / Group Housing

METRO LIFE ULTIMA RESIDENCES PHASE II

RAMA SYNERGY SPACES · Tathwade · Mulshi

Aug 2023registered
Jun 2028target completion
Government Guidance Rate₹58,805/sq ydScale182 flatsAuthorityMahaRERA
590 m awayOthers

Yashwin Urbo Centro Phase 2

Vilas Javdekar Infinitee Developers Pvt. Ltd. · Wakad · Mulshi

Oct 2024registered
Jun 2029target completion
1 open complaintGovernment Guidance Rate₹68,746/sq ydScale1,039 flatsAuthorityMahaRERA
620 m awayResidential / Group Housing

Ganga Aurum Park C

Ecostar Goel Properties LLP · Tathwade · Mulshi

Nov 2017registered
Dec 2026target completion
1 open complaintGovernment Guidance Rate₹58,805/sq ydScale103 flatsAuthorityMahaRERA
670 m awayResidential / Group Housing

YASHWANT AUDUMBAR A WING

AKRUTI PROMOTERS AND DEVELOPERS · Tathwade · Mulshi

Apr 2023registered
Mar 2026target completion
Government Guidance Rate₹58,805/sq ydScale34 flatsAuthorityMahaRERA
670 m awayResidential / Group Housing

YASHWANT AUDUMBAR B WING

AKRUTI PROMOTERS AND DEVELOPERS · Tathwade · Mulshi

Jul 2023registered
Mar 2026target completion
Government Guidance Rate₹58,805/sq ydScale41 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.