Merlin Ventana

P52100053687 · MahaRERA · https://gethorizon.in/projects/merlin-ventana-baner-haveli-8vfujzmn

01

Complete project overview

MahaRERA · Registration filing
Project name
Merlin Ventana
Units
255 units
Floors
30
Buildings
6
Parking
645 spaces
Land area
4,378 sq m
Sanctioned built-up
36,306 sq m
Recreational open space
1,181 sq m

Timeline

RERA registeredNov 2023
Proposed completionDec 2028
TodaySep 2026
Construction progress
Stilt floor0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Superstructure4%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

MERLIN BHINGARWALA DEVELOPERS LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
2Projects
2Cities
2023–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
661 homeson the public record across 2 projects
75,246 sq mbuilt-up filed
15,468 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 2 projects
Pune Municipal CorporationMunicipal Corporationthis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from MERLIN BHINGARWALA DEVELOPERS LLP— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Baner
Taluka
Haveli
District
Pune
Pincode
411045
Survey no.
111/11/1 (Part)
North boundary
12 meter Internal road
East boundary
Survey No 112
South boundary
Remaining portion out of Survey No 111
West boundary
Remaining portion out of Survey No 111
What’s nearby
SchoolsNearest school 1.3km away · College or university 1.4km away
HealthcareHospital 806m away · 1 clinic within 1km
LifestylePark 1.6km away · Gym or sports centre 799m away
ShoppingSupermarket 1.6km away
Getting around
Expressway 4.2 kmPrimary road 1.9 km · Hinjawadi Phase 2 RoadMetro station 1.9km away (Infosys)Limited bus connectivity nearby
Water & environment
Water body 334 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹76,606per sq yd
₹91,620per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “Baner”.
In force
2026-2027 schedule
Spread
₹42,233₹88,337 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 111/11/1 (Part)
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Pune Municipal Corporation

Municipal corporation

Has approved 1,863 RERA projectsabout 1 in 11 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,351
On record
9,749 flats · 439 plots
Reach
3 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

2,761 residential projects still under way within 25 km. Step out ring by ring:

Of the 986 projects the radar draws within 6 km — every kind, every stage — 367 are residential projects still under way. This list keeps only those, and looks further out.

14 projects within 1 km — showing the nearest 6.

670 m awayResidential / Group Housing

Niwas

Ashiana Housing Limited · Marunji · Mulshi

Dec 2023registered
Jan 2029target completion
Scale360 flatsAuthorityMahaRERA
670 m awayResidential / Group Housing

ASHIANA MALHAR PHASE III

Ashiana Housing Limited · Marunji · Mulshi

Jun 2024registered
Mar 2028target completion
Scale220 flatsAuthorityMahaRERA
800 m awayResidential / Group Housing

Prithvi Paradise NXT

M/s Pruth V Buildmasters LLP · Tathwade · Mulshi

Jun 2024registered
Oct 2027target completion
Government Guidance Rate₹58,805/sq ydScale237 flatsAuthorityMahaRERA
870 m awayResidential / Group Housing

Ashiana Malhar Phase II

Ashiana Housing Limited · Marunji · Mulshi

Sep 2023registered
May 2027target completion
Scale220 flatsAuthorityMahaRERA
890 m awayResidential / Group Housing

MORELLA PHASE II

Buchade Patil Developers · Marunji · Mulshi

Mar 2020registered
Dec 2026target completion
Scale81 flatsAuthorityMahaRERA
930 m awayResidential / Group Housing

PARK TITAN PHASE II

PRIDE PURPLE INFRASTRUCTURE · Marunji · Mulshi

Apr 2022registered
Jun 2026target completion
AuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.