HORIZON
Share

Om Dutta Deep Co. Op HSG

P51700054486 · MahaRERA · https://gethorizon.in/projects/om-dutta-deep-co-op-hsg-badlapur-m-cl-ambarnath-22gmyp04

01

Complete project overview

MahaRERA · Registration filing
Units
32 units
Floors
8
Buildings
2
Parking
55 spaces
Land area
522 sq m
Sanctioned built-up
1,805 sq m

Timeline

RERA registeredJan 2024
Proposed completionDec 2025
TodaySep 2026
Construction progress
Podiums0%
Stilt floor0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Water conservation…0%
Open Parking0%
Superstructure92%
Excavation100%
Basement (if any)100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Shree Samarth Enterprises

PartnershipPromoter type
Thane, MAHARASHTRABased in
4Projects
2Cities
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
356 homeson the public record across 4 projects
18,866 sq mbuilt-up filed
9,136 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kulgaon Badlapur Municipal CouncilMunicipal Councilthis project3 of 4 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporation1 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Shree Samarth Enterprises— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Badlapur (M Cl)
Taluka
Ambarnath
District
Thane
Pincode
421503
Survey no.
Survey No 16/1/21/1/2/3
North boundary
18 MT wide road
East boundary
ADJ 6 Mt Wide Road
South boundary
ADJ Maharwada
West boundary
Plot No 2
What’s nearby
SchoolsNo schools within 2km · Library 977m away
HealthcareHospital 868m away · Clinic within 2km
Lifestyle1 park within 500m · 3 restaurants and cafes within 1km
ShoppingNo supermarket within 2km
Getting around
Primary road 51 m · Pipeline RoadRailway line 214 m · Mumbai-Pune RailwayRailway station 1.7km away (Badlapur)Bus stop within 1km
Water & environment
Water body 369 m · Lotus Pond
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹44,064per sq yd
₹52,700per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “Badlapur (M Cl)”.
In force
2026-2027 schedule
Spread
₹41,639₹44,064 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Kulgaon Badlapur Municipal Council

Municipal Council
Building Permit
Survey no. Survey No 16/1/21/1/2/3

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Kulgaon Badlapur Municipal Council

Municipal corporation

Has approved 119 RERA projects0.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
102
On record
860 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

2,317 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,297 projects the radar draws within 6 km — every kind, every stage — 374 are residential projects still under way. This list keeps only those, and looks further out.

63 projects within 1 km — showing the nearest 6.

BadlapurResidential / Group Housing

SHREEJI MILESTONE

DEEP LAXMI ASSOCIATES

Apr 2023registered
Jun 2029target completion
Government Guidance Rate₹44,064/sq ydScale530 flatsAuthorityMahaRERA
BadlapurResidential / Group Housing

PATIL HIGHLANDS PHASE I WING C

SAS INFRA

Jan 2023registered
Dec 2026target completion
Government Guidance Rate₹44,064/sq ydAuthorityMahaRERA
BadlapurResidential / Group Housing

Patil Highlands Phase II Wing B

SAS INFRA

Aug 2025registered
Dec 2028target completion
Government Guidance Rate₹44,064/sq ydScale115 flatsAuthorityMahaRERA
BadlapurResidential / Group Housing

THARWANI MILLENNIUM CITY PHASE III

THARWANI REALTORS

Jan 2020registered
Dec 2026target completion
Government Guidance Rate₹44,064/sq ydScale103 flatsAuthorityMahaRERA
BelavliResidential / Group Housing

R1 AND R2 PANVELKAR PALASH CHS

Shree Sai Enterprises

Jun 2026registered
Dec 2029target completion
Government Guidance Rate₹48,495/sq ydScale87 flatsAuthorityMahaRERA
BelavliResidential / Group Housing

INFINITY MEADOWS

INFINITY REALTY

Sep 2026registered
Dec 2030target completion
Government Guidance Rate₹48,495/sq ydScale42 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.