OM HARMONY

PM1270002500515 · MahaRERA · https://gethorizon.in/projects/om-harmony-ulawe-panvel-uz5oyexu

01

Complete project overview

MahaRERA · Registration filing
Units
68 units
Floors
8
Buildings
4
Parking
87 spaces
Land area
1,000 sq m
Sanctioned built-up
3,996 sq m

Timeline

RERA registeredAug 2025
Proposed completionMay 2029
TodaySep 2026
Construction progress
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Water conservation…0%
Electrical meter r…0%
Open Parking0%
Superstructure30%
Excavation100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Om Builders & Developers

PartnershipPromoter type
Thane, MAHARASHTRABased in
5Projects
4Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
105 homes · 24 plotson the public record across 5 projects
6,100 sq mbuilt-up filed
3,481 sq mland declared
₹3.67 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
City and Industrial Development Corporation (CIDCO)Development Authoritythis project1 of 4 projects
Lanja Nagar PanchayatMunicipal Council1 of 4 projects
RewaTown & Country Planning (DTCP)1 of 4 projects
Special Planning Authority, Jeypore1 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Om Builders & Developers— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Ulawe
Taluka
Panvel
District
Raigarh
Pincode
410206
Survey no.
Plot No. 162 of Sector 9
North boundary
North
East boundary
East
South boundary
South
West boundary
West
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.9km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.0 km · Ulwe FlyoverPrimary road 2.6 km · Panvel Uran RoadRailway line 530 m · Uran LineNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 348 m · CIDCO PondCanal 653 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

City and Industrial Development Corporation (CIDCO)

Development Authority
Building Permit
Survey no. Plot No. 162 of Sector 9
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

City and Industrial Development Corporation (CIDCO)

Metropolitan / development authority

Has approved 885 RERA projectsabout 1 in 23 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
724
On record
7,061 flats · 987 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,217 residential projects still under way within 25 km. Step out ring by ring:

Of the 904 projects the radar draws within 6 km — every kind, every stage — 217 are residential projects still under way. This list keeps only those, and looks further out.

19 projects within 1 km — showing the nearest 6.

110 m awayResidential / Group Housing

HILL CREST

SH BUILDCON · Ulawe · Panvel

Mar 2025registered
Dec 2029target completion
Scale126 flatsAuthorityMahaRERA
110 m awayResidential / Group Housing

ND Garden

Shree Gajanand Developers · Ulawe · Panvel

Oct 2021registered
Dec 2026target completion
Scale41 flatsAuthorityMahaRERA
130 m awayResidential / Group Housing

ND Garden Tower

Shree Gajanand Developers · Ulawe · Panvel

Nov 2021registered
Dec 2026target completion
Scale33 flatsAuthorityMahaRERA
160 m awayResidential / Group Housing

HILLCREST

ERDAMOR REALTY LLP · Ulawe · Panvel

Jul 2024registered
Dec 2027target completion
Scale26 flatsAuthorityMahaRERA
190 m awayResidential / Group Housing

Neels West Wind

Neel Realtors · Ulawe · Panvel

Aug 2022registered
Dec 2026target completion
Scale104 flatsAuthorityMahaRERA
190 m awayResidential / Group Housing

VAIKUNTH BLISS

DIVYESH DILIPBHAI NAKRANI · Ulawe · Panvel

Jun 2024registered
Dec 2026target completion
Scale42 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.