MICRON RESIDENCY

P51700047065 · MahaRERA · https://gethorizon.in/projects/micron-residency-ulawe-panvel-73cuvfnj

01

Complete project overview

MahaRERA · Registration filing
Units
61 units
Floors
9
Buildings
2
Parking
92 spaces
Land area
1,098 sq m
Sanctioned built-up
1,207 sq m

Timeline

RERA registeredSep 2022
Proposed completionJul 2026
TodaySep 2026
Construction progress
Podiums0%
Water Supply0%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Sewerage (Chamber,…100%
Landscaping & Tree…100%
Water conservation…100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

MICRON INFRA

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2022–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Ulawe
Taluka
Panvel
District
Raigarh
Pincode
410206
Survey no.
PLOT NO 323
North boundary
PLOT NO 317 AND 318
East boundary
PLOT NO 324
South boundary
20 MTR WIDE ROAD
West boundary
PLOT NO 321 AND 322
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.1km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.2 km · FlyoverPrimary road 1.6 km · Panvel Uran RoadRailway line 586 m · Uran LineNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Canal 57 mWater body 271 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

City and Industrial Development Corporation (CIDCO)

Development Authority
Building Permit
Survey no. PLOT NO 323

The promised possession date (31 Jul 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

City and Industrial Development Corporation (CIDCO)

Metropolitan / development authority

Has approved 885 RERA projectsabout 1 in 23 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
724
On record
7,061 flats · 987 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,024 residential projects still under way within 25 km. Step out ring by ring:

Of the 973 projects the radar draws within 6 km — every kind, every stage — 278 are residential projects still under way. This list keeps only those, and looks further out.

45 projects within 1 km — showing the nearest 6.

130 m awayOthers

Devpriya

SHREE CHAMUNDA REALTY · Ulawe · Panvel

Aug 2023registered
Jun 2027target completion
Scale80 flatsAuthorityMahaRERA
230 m awayResidential / Group Housing

BHAVESHWAR INFINITY

SHREENATHJI ENTERPRISES · Ulawe · Panvel

Jun 2025registered
Dec 2030target completion
Scale101 flatsAuthorityMahaRERA
240 m awayMixed

D N HERITAGE

DOSTY NEELKANTH INFRA · Ulawe · Panvel

Sep 2025registered
Dec 2029target completion
Scale49 flatsAuthorityMahaRERA
280 m awayResidential / Group Housing

BHAKTI HILL

DIYA ASSOCIATES · Ulawe · Panvel

Mar 2025registered
Dec 2028target completion
Scale47 flatsAuthorityMahaRERA
290 m awayResidential / Group Housing

ROYAL PALM

MARQUIS BUILDERS · Ulawe · Panvel

Feb 2022registered
Dec 2026target completion
Scale140 flatsAuthorityMahaRERA
330 m awayMixed

NORTH ONE

ASHTAVINAYAK DEVELOPERS · Ulawe · Panvel

Jun 2026registered
Mar 2031target completion
Scale78 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.