01

Complete project overview

MahaRERA · Registration filing
Units
17 units
Floors
6
Buildings
2
Parking
4 spaces
Land area
250 sq m
Sanctioned built-up
375 sq m

Timeline

RERA registeredJul 2020
Proposed completionSep 2025
TodaySep 2026
Construction progress
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Electrical meter r…0%
Open Parking0%
Excavation100%
Basement (if any)100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Maruti Infra Developers

PartnershipPromoter type
Thane, MAHARASHTRABased in
3Projects
1City
2018–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
46 homeson the public record across 3 projects
1,124 sq mbuilt-up filed
750 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Maruti Infra Developers— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Ulawe
Taluka
Panvel
District
Raigarh
Pincode
400206
Survey no.
197
North boundary
11 M Wide Road
East boundary
Plot no 196
South boundary
Plot no 179
West boundary
Plot no 198
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.1km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.2 km · FlyoverPrimary road 1.6 km · Panvel Uran RoadRailway line 586 m · Uran LineNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Canal 57 mWater body 271 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

City and Industrial Development Corporation (CIDCO)

Development Authority
Building Permit
Survey no. 197

The promised possession date (30 Sep 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

City and Industrial Development Corporation (CIDCO)

Metropolitan / development authority

Has approved 885 RERA projectsabout 1 in 23 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
724
On record
7,061 flats · 987 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,025 residential projects still under way within 25 km. Step out ring by ring:

Of the 973 projects the radar draws within 6 km — every kind, every stage — 279 are residential projects still under way. This list keeps only those, and looks further out.

46 projects within 1 km — showing the nearest 6.

10 m awayResidential / Group Housing

MICRON RESIDENCY

MICRON INFRA · Ulawe · Panvel

Sep 2022registered
Jul 2026target completion
Scale61 flatsAuthorityMahaRERA
130 m awayOthers

Devpriya

SHREE CHAMUNDA REALTY · Ulawe · Panvel

Aug 2023registered
Jun 2027target completion
Scale80 flatsAuthorityMahaRERA
230 m awayResidential / Group Housing

BHAVESHWAR INFINITY

SHREENATHJI ENTERPRISES · Ulawe · Panvel

Jun 2025registered
Dec 2030target completion
Scale101 flatsAuthorityMahaRERA
240 m awayMixed

D N HERITAGE

DOSTY NEELKANTH INFRA · Ulawe · Panvel

Sep 2025registered
Dec 2029target completion
Scale49 flatsAuthorityMahaRERA
280 m awayResidential / Group Housing

BHAKTI HILL

DIYA ASSOCIATES · Ulawe · Panvel

Mar 2025registered
Dec 2028target completion
Scale47 flatsAuthorityMahaRERA
290 m awayResidential / Group Housing

ROYAL PALM

MARQUIS BUILDERS · Ulawe · Panvel

Feb 2022registered
Dec 2026target completion
Scale140 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.