HORIZONMarkets
01

Complete project overview

UP-RERA · Registration filing
Units
414 units
Unit mix
300 × 2 BHK · 114 × 3 BHK
Carpet area
53–84 sq mper unit, as filed
Floors
25
Blocks
3
Land area
8,922 sq m

Timeline

Project startedOct 2016
RERA registeredAug 2017
Proposed completionAug 2021
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

414 units across 69 batches
BuildingFloorTypeArea sq mCount
D113 BHK846
D123 BHK846
D133 BHK846
D143 BHK846
D153 BHK846
D163 BHK846
D173 BHK846
D183 BHK846
D193 BHK846
D1103 BHK846
D1113 BHK846
D1123 BHK846
D1133 BHK846
D1143 BHK846
D1153 BHK846
D1163 BHK846
D1173 BHK846
D1183 BHK846
D1193 BHK846
D212 BHK656
D222 BHK656
D232 BHK656
D242 BHK656
D252 BHK656
D262 BHK656
D272 BHK656
D282 BHK656
D292 BHK656
D2102 BHK656
D2112 BHK656
D2122 BHK656
D2132 BHK656
D2142 BHK656
D2152 BHK656
D2162 BHK656
D2172 BHK656
D2182 BHK656
D2192 BHK656
D2202 BHK656
D2212 BHK656
D2222 BHK656
D2232 BHK656
D2242 BHK656
D2252 BHK656
E512 BHK536
E522 BHK536
E532 BHK536
E542 BHK536
E552 BHK536
E562 BHK536
E572 BHK536
E582 BHK536
E592 BHK536
E5102 BHK536
E5112 BHK536
E5122 BHK536
E5132 BHK536
E5142 BHK536
E5152 BHK536
E5162 BHK536
E5172 BHK536
E5182 BHK536
E5192 BHK536
E5202 BHK536
E5212 BHK536
E5222 BHK536
E5232 BHK536
E5242 BHK536
E5252 BHK536

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

PANCHSHEEL BUILDTECH PVT. LTD.

CompanyPromoter type
18Registered projects
18Projects
2Cities
2017–2022Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
7,895 homeson the public record across 18 projects
2,51,983 sq mland declared
₹2720.72 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Gautam Buddha Nagar
Tehsil
Select
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.8km away
LifestyleNo parks within 2km · Gym or sports centre 1.8km away
ShoppingSupermarket 1.8km away
Getting around
Expressway 2.7 km · Grand Trunk RoadRailway line 1.6 kmRailway station 4.1km away (Maripat)Limited bus connectivity nearby
Water & environment
Water body 346 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹119.84 Cr declared to build 414 flats. What that works out to:

₹28.95 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 25 Nov 2014 · 11 yrs ago
Building Permit no. BP-3089/GH/FTS-8857

The promised possession date (31 Aug 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Completion Certificate — the occupancy sign-off, on record

A Completion Certificateis on this project’s RERA record (dated 4 Oct 2023)— the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit before you rely on it.

Verify it yourself — look up plan BP-3089/GH/FTS-8857 on the approving authority’s portal to confirm the sanction.

Complaints register

11 complaints on UP-RERA’s register for this project.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.