HORIZONMarkets
01

Complete project overview

UP-RERA · Registration filing
Units
80 units
Unit mix
80 × 3 BHK
Carpet area
92 sq mper unit, as filed
Floors
4
Blocks
8
Land area
4,946 sq m

Timeline

RERA registeredAug 2017
Project startedAug 2017
Proposed completionAug 2021
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

80 units across 40 batches
BuildingFloorTypeArea sq mCount
Block06GF3 BHK922
Block0613 BHK922
Block0623 BHK922
Block0633 BHK922
Block0643 BHK922
Block07GF3 BHK922
Block0713 BHK922
Block0723 BHK922
Block0733 BHK922
Block0743 BHK922
Block08GF3 BHK922
Block0813 BHK922
Block0823 BHK922
Block0833 BHK922
Block0843 BHK922
Block09GF3 BHK922
Block0913 BHK922
Block0923 BHK922
Block0933 BHK922
Block0943 BHK922
Block10GF3 BHK922
Block1013 BHK922
Block1023 BHK922
Block1033 BHK922
Block1043 BHK922
Block11GF3 BHK922
Block1113 BHK922
Block1123 BHK922
Block1133 BHK922
Block1143 BHK922
Block12GF3 BHK922
Block1213 BHK922
Block1223 BHK922
Block1233 BHK922
Block1243 BHK922
Block13GF3 BHK922
Block1313 BHK922
Block1323 BHK922
Block1333 BHK922
Block1343 BHK922

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

PANCHSHEEL BUILDTECH PVT. LTD.

CompanyPromoter type
18Registered projects
18Projects
2Cities
2017–2022Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
7,895 homeson the public record across 18 projects
2,51,983 sq mland declared
₹2720.72 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Ghaziabad
Tehsil
Ghaziabad
What’s nearby
Schools2 schools within 1km · Library 1.2km away
HealthcareHospital 535m away · 1 clinic within 1km
LifestylePark 1.0km away · Gym or sports centre 1.8km away
ShoppingSupermarket 1.6km away · Mall 1.4km away
Getting around
Expressway 709 m · FlyoverPrimary road 4.7 km · Raj Nagar Extension Road FlyoverRailway line 1.1 kmRailway station 4.2km away (Guldhar)Limited bus connectivity nearby
Water & environment
Water body 1.1 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹32.06 Cr declared to build 80 flats. What that works out to:

₹40.08 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 22 Dec 2015 · 10 yrs ago
Building Permit no. 390/ZONE - 4/14-15

The promised possession date (31 Aug 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Completion Certificate — the occupancy sign-off, on record

A Completion Certificateis on this project’s RERA record (dated 2 Dec 2024)— the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit before you rely on it.

Verify it yourself — look up plan 390/ZONE - 4/14-15 on the approving authority’s portal to confirm the sanction.

Complaints register

None on record with UP-RERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.