Complete project overview

MahaRERA · Registration filing
Floors
17
Buildings
2
Parking
31 spaces
Land area
842 sq m
Sanctioned built-up
2,141 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2021
TodayJul 2026
Construction progress
Podiums0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Fire protection an…0%
Electrical meter r…0%
Open Parking0%
Flat fit-out7%
Internal finishes33%
Stairs & lifts64%
Superstructure70%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Mishal Construction Private Limited

CompanyPromoter type
Mumbai City, MAHARASHTRABased in
4Projects
1City
2017–2021Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
27 homeson the public record across 4 projects
5,511 sq mbuilt-up filed
2,498 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Maharashtra Housing and Area Development Authority (MHADA)Housing Authoritythis project1 of 2 projects
Municipal Corporation of Greater MumbaiMunicipal Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kurla
Taluka
Kurla
District
Mumbai Suburban
Pincode
400075
Survey no.
CTS No. 194 Survey No. 236A
North boundary
40 feet Road
East boundary
Bldg No 24
South boundary
Building number 23
West boundary
40 feet wide road
What’s nearby
SchoolsNearest school 1.0km away · Library 1.9km away
HealthcareHospital 209m away · Clinic within 2km · Pharmacy within 1km
Lifestyle1 park within 500m · Gym or sports centre 594m away · 5 restaurants and cafes within 1km
ShoppingSupermarket 1.9km away · Bank 491m away
Getting around
Expressway 10 m · Eastern Express HighwayPrimary road 586 m · Vasantdada Patil MargRailway line 1.1 km · Central Railways Express LineRailway station 1.1km away (Ghatkopar)2 bus stops within 500m
Water & environment
Water body 1.4 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Maharashtra Housing and Area Development Authority (MHADA)

Housing Authority
Building Permit
Survey no. CTS No. 194 Survey No. 236A

The promised possession date (30 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra Housing and Area Development Authority (MHADA)

Planning authority

Has approved 438 RERA projects2.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
341
On record
13,458 flats · 0 plots
Reach
18 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
Compliance4 non-compliance notices on record
Appeals4 appeals before the tribunal
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

5 complaints on MahaRERA’s register for this project 5 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.