PUSHPRAJ PRIME

PM1330002500846 · MahaRERA · https://gethorizon.in/projects/pushpraj-prime-ulhasnagar-m-corp-oc3j4aen

01

Complete project overview

MahaRERA · Registration filing
Units
181 units
Floors
13
Buildings
2
Parking
347 spaces
Land area
2,879 sq m
Sanctioned built-up
8,584 sq m

Timeline

RERA registeredSep 2025
Proposed completionMay 2028
TodaySep 2026
Construction progress
Water Supply0%
Sewerage (Chamber,…0%
Treatment And Disp…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Plinth54%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

MOONSTONE PROPERTIES

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Ulhasnagar (M Corp.)
Taluka
Ulhasnagar
District
Thane
Pincode
421003
Survey no.
C.T.S. No. 30803 (P) , Plot bearing No.157, Section 4-B, SHEET NO. 34
North boundary
ROAD
East boundary
MAIN ENTRANCE AND ROAD
South boundary
BARRACKS
West boundary
REMAINING PORTION OF PLOT NO 157 SECTION 4B
What’s nearby
SchoolsNearest school 1.9km away
HealthcareHospital 501m away · 1 clinic within 1km
LifestylePark 1.3km away
ShoppingNo supermarket within 2km
Getting around
Expressway 1.9 km · Ahilyanagar - Kalyan Road | Bhiwandi - Murbad Road | B K Birla RoadPrimary road 499 m · Kalyan Badlapur RoadRailway line 91 m · Mumbai-Pune RailwayRailway station 579m away (Vithalwadi)Limited bus connectivity nearby
Water & environment
River 410 m · Waldhuni RiverWater body 646 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Ulhasnagar Municipal Corporation

Municipal Corporation
Building Permit
Survey no. C.T.S. No. 30803 (P) , Plot bearing No.157, Section 4-B, SHEET NO. 34
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Ulhasnagar Municipal Corporation

Municipal corporation

Has approved 37 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
32
On record
283 flats · 0 plots
Since
2019

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

2,698 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,622 projects the radar draws within 6 km — every kind, every stage — 606 are residential projects still under way. This list keeps only those, and looks further out.

23 projects within 1 km — showing the nearest 6.

280 m awayResidential / Group Housing

HILTRON HILLS

HILLVIEW REALTY · Ulhasnagar

Jan 2024registered
Dec 2027target completion
Scale50 flatsAuthorityMahaRERA
280 m awayOthers

GLOBAL HEIGHTS

GLOBAL BUILDERS AND DEVELOPERS · Ulhasnagar

Jul 2023registered
Dec 2027target completion
Scale67 flatsAuthorityMahaRERA
280 m awayResidential / Group Housing

DEVI HILLS

SAI RAM DEVELOPERS · Ulhasnagar

Apr 2024registered
Dec 2026target completion
Scale21 flatsAuthorityMahaRERA
280 m awayOthers

SHARDA ROYCE

SHARDA HOMES · Ulhasnagar

Sep 2023registered
Dec 2028target completion
Scale105 flatsAuthorityMahaRERA
510 m awayOthers

Prakash Palace

R K Builders and Developers · Ambarnath

Feb 2025registered
Dec 2026target completion
Government Guidance Rate₹47,492/sq ydScale23 flatsAuthorityMahaRERA
510 m awayResidential / Group Housing

OM MAHESH CO-OPERATIVE HOUSING SOCIETY LIMITED

RAMUGRAH LALBIHARI SINGH · KHADEGOLAVALI · Kalyan

Aug 2024registered
Mar 2029target completion
Government Guidance Rate₹48,579/sq ydScale55 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.