HORIZON
Share

Saivishwa

P51900005928 · MahaRERA · https://gethorizon.in/projects/saivishwa-mumbai-city-muqd7wc1

Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Units
28 units
Floors
16
Buildings
2
Parking
24 spaces
Land area
812 sq m
Sanctioned built-up
526 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2019
TodaySep 2026
02

Builder’s track record

MahaRERA · Builder registration

Snehalkumar Chandrakant Nadkarni

IndividualPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2017–2019Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Mumbai City
Taluka
Mumbai City
District
Mumbai City
Pincode
400089
Survey no.
CTS no 582,582-1 to 9
North boundary
CTS NO 554
East boundary
CTS NO 589
South boundary
J N PATIL Road
West boundary
Boundary of Chembur Village
What’s nearby
Schools1 school within 1km · Library 554m away
HealthcareHospital 172m away · 6 clinics within 1km · Pharmacy within 500m
Lifestyle1 park within 500m · Gym or sports centre 554m away · 19+ restaurants and cafes within 1km
ShoppingSupermarket 270m away · Convenience store within 1km · Bank 624m away
Getting around
Expressway 200 mPrimary road 2.0 km · Lal Bahadur Shastri MargRailway line 567 m · Central Railway (Harbour Line)Railway station 662m away (Chembur)2 bus stops within 500m
Water & environment
Water body 615 m · Trombay Creek
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. CTS no 582,582-1 to 9

The promised possession date (31 Dec 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

4,474 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,735 projects the radar draws within 6 km — every kind, every stage — 536 are residential projects still under way. This list keeps only those, and looks further out.

39 projects within 1 km — showing the nearest 6.

30 m awayResidential / Group Housing

Atmosphere O2

Atmosphere Realty Pvt Ltd · Kurla

Mar 2019registered
Dec 2026target completion
Scale830 flatsAuthorityMahaRERA
180 m awayResidential / Group Housing

Serenity- Bldg 1

JVPD Properties Private Limited · Kurla

Aug 2017registered
Jul 2026target completion
2 open complaintsScale86 flatsAuthorityMahaRERA
250 m awayResidential / Group Housing

Premia Towers B and C

Kenarc Spaces LLP · Chembur · Kurla

May 2025registered
Dec 2027target completion
Government Guidance Rate₹1,04,432/sq ydScale117 flatsAuthorityMahaRERA
260 m awayResidential / Group Housing

Shivam Sunview

Shivam Lifestyle · Chembur · Kurla

May 2025registered
Dec 2027target completion
Government Guidance Rate₹1,37,627/sq ydAuthorityMahaRERA
270 m awayResidential / Group Housing

One Avenue

SURYANAGRI BUILDERS LLP · Chembur · Kurla

Sep 2024registered
May 2028target completion
Scale21 flatsAuthorityMahaRERA
320 m awayOthers

Silicon Pride

Silicon Lifespaces LLP · Chembur · Kurla

Jun 2024registered
Nov 2027target completion
Government Guidance Rate₹1,37,627/sq ydScale247 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.